Investing in our Neighborhoods

MAYSVILLE ROAD ENHANCEMENT

Contractor: S & S Directional
Start date:  Spring 2018
Completion Date: 
Investment:  

Description: This project involves the widening of roadway from 2-lane to 4-lanes, with center turn, from Stellhorn Road to Meijer Drive. It also includes improved sidewalk on east side and trail on west side, two pedestrain bridges, storm sewers, water main and sanitary sewer.

 

3 FINAL LOOKING NORTH AT BRIDGE   4 FINAL LOOKING SOUTH ON MAYSVILLE

Investing in our Neighborhoods

NORTH ANTHONY BOULEVARD

Contractor: 
Start date:  Spring 2018
Completion Date: 
Investment: 

 Description: This project -- which runs from Coliseum Boulevard to Crescent Avenue -- will include the reconstruction of concrete pavement, including curbs, sidewalk repair, upgrade ADA curb ramps, decorative street lighting and replace drive approaches as needed.

Investing in our Neighborhoods

OXFORD STREET

Completion date: Sept. 10, 2015
Contractor: Primco, Inc.
Investment: $1.33 million

pdfOxford_Street__Plans.pdf

Description: Project includes spot repair and reconstruction of concrete on Oxford Street from South Anthony Boulevard to Turpie Street.

Improvements include installation of a "road diet," which reduces the number of travel lanes on the street.

In addition, work will include the repair and replacement of sidewalks and updating of ADA (American with Disabilities Act) sidewalk ramps.

PLEASE DO NOT MOVE BARRICADES

Newly poured concrete needs 7 days to cure. Do NOT move barricades and drive over concrete that is curing. It can damage the concrete, reduce the pavement’s life  -- causing it to crumble within months. Please be vigilant and stop people from moving barricades.

UPDATE (OCTOBER 2015):  Contractor will complete the work at the intersection of S. Anthony Blvd. General clean-up and completion of backfill and hydro-seed operations.

UPDATE (OCTOBER 2015): Paving of the McMillen Pk. Pump station drive approach, located at the back side of the park shared-use trail. Parkstrip restoration on the south side of Oxford Street.

UPDATE (SEPTEMBER 2015): Contractor is paving of the remainder of the south-side main-line (East) roadway, Parks main entrance off of Oxford St., sidewalk / drive connections, and trail construction within McMillen Park boundary.

UPDATE  (August,2015): Contractor has begun paving of sidewalks, pedestrian refuge islands, residential and alley drive approaches; will finish grading, top soil, and hydro-seeding operations on the north side of Oxford St. Traffic change has been installed to utilize the north side of Oxford St., allowing for construction on the south side of the roadway. Construction moving along on the southside of Oxford St. as planned. Pipe and structure work in motion. All proposed demolition on roadway completed.

UPDATE  (July 31, 2015): Work completed includes paving of sidewalks, pedistrian refuge islands, residential and alley drive approaches; will finish grading, top soil, and hydro-seeding operations on the north side of Oxford St. Traffic change to utilize the north side of Oxford St., allowing for construction on the south side of the roadway.

Contractor also plans to continue demolition of the remainder of Oxford St., placing underdrain, storm sewer pipe and structure installation.

UPDATE (July 20, 2015): The contractor is expected to close the open side of the street and open the closed side. Traffic will still be one-way, but will be moved to the other side of the street.

UPDATE (July 1, 2015): Paved roadway and began working to pave adjacent street connections. Contractor is working to form and pour street approaches, sidewalk, drives, and curb-ramps (north side of Oxford St.) to connect to adjacent pavements.

UPDATE (June 9, 2015): Contractor will work to rub out the curb-face sidewalk from Lillie St. to S. Anthony Blvd. Resolving unforseen utility conflicts.

UPDATE  (June 15, 2015): Contractor continues to form and pour street approaches, sidewalk, drives, and curb-ramps (north side of Oxford St.) to connect to adjacent pavements.

 UPDATE (June 2, 2015):  Construction is currently active on the north side of the roadway from S. Anthony Blvd. through to Turpie St. Operations includes: removal of pavement, sidewalk and drives; installation of drainage structures, including underdrain. The sub-base has passed intial proof-rolling tests and base materials have been compacted in place to prepare for the proposed concrete pavement. Paving began this week.

UPDATE (April 17, 2015): Please be advised that on Friday April 17, 2015 Oxford Street will be under a new traffic pattern between South Anthony Boulevard and Wayne Trace.

Oxford Street will temporarily become 1-way traffic heading east from South Anthony Boulevard towards Wayne Trace.  This change will remain in place during the Oxford Street improvement project which is anticipated to complete in September. Adjacent streets will be periodically affected due to construction phasing.

The project will improve circulation and safety for vehicular, bicycle and pedestrian traffic on Oxford. It includes concrete road reconstruction; trails on both sides of the road, ADA curb ramps, and a grass park strip.

Primco, Inc. will be doing the work and will be responsible for the placement and maintenance of all construction signs and barricades in the work zone.

P82A1251

 

Investing in our Neighborhoods

NORTH FRANKE PARK

Contractor:  TBA
Start date:   2018
Completion Date: TBA
Investment: TBA

Description: Project includes spot repair and reconstruction of concrete streets in the North Franke Park neighborhood.

Improvements also include repair and reconstruction of some curbs and sidewalks, and the installation of some ADA (Americans with Disabilities Act) curb ramps.

 

Frank Franke

 

Check back soon for more information!

 

 

Investing in our Neighborhoods

PINE VALLEY/WINDRIFT – Phase II

Contractor: Hipskind Concrete
Start date:  Spring 2018
Completion Date:  TBA
Investment: TBA

 Description: This project involves spot repair, reconstruction of concrete streets & sidewalks and storm drainage improvements in the Pine Valley and Windrift neighborhoods. It will also include affected drive approaches & curb ramps. This is the second phase of improvement work being done in these two neighborhoods.

 

Frank Pine2 

 

PLEASE DO NOT MOVE BARRICADES

Newly poured concrete needs 7 days to cure. Do NOT move barricades and drive over concrete that is curing. It can damage the concrete, reduce the pavement’s life  -- causing it to crumble within months. Please be vigilant and stop people from moving barricades.

Parking: Residents may not have access to their driveway while work is being done on the section of their street. Please park away from construction and DO NOT block traffic lanes.

Trash & Recycling Collection: The night before collection day, residents should place their garbage and recycling containers near the curb, away from the barricades of construction zones for collection – which may be across the street or at the end of the cul-de-sac.

If garbage collection trucks are not able to get to your street, due to construction work, they will try to collect the next day, before construction begins in the morning. For more information, call 311.

Neighborhood Engagement: Public Works staff members have been meeting with neighborhood associations to give residents the opportunity to view work zones, meet the contractors and ask questions about work being done in their neighborhoods. For questions or concerns, you may reach the Division of Public Works by calling 311 or 427-8311.

Page 2 of 2