Investing in our Neighborhoods

HAVERHILL /ABOITE LAKE ESTATES /PLANTATIONS OF ABOITE-NORTH SHORES NEIGHBORHOOD

Completion date:  June 30*  *Project delayed due to record rainfall in June; completion expected by end of September
Contractor: Garcia Concrete
Investment: $1.97 million

Map391.75 KB Haverhill_Plan.pdf11.11 MB

Project includes spot repair and reconstruction of concrete streets and affected drive approaches in the Haverhill, Aboite Lake Estates and Plantations of Aboite neighborhoods, as well as installation of underdrains and stormwater upgrades.

Improvement work also includes repair and replacement of some sidewalks and updating ADA (Americans with Disabilities Act) sidewalk curb ramps.

PLEASE DO NOT MOVE BARRICADES

Newly poured concrete needs 7 days to cure. Do NOT move barricades and drive over concrete that is curing. It can damage the concrete, reduce the pavement’s life  -- causing it to crumble within months. Please be vigilant and stop people from moving barricades.

UPDATE: (Oct. 1, 2015) -- All concrete has been substantially completed and the contractor will be backfilling next week and fixing spots that are on the punch list.

UPDATE:  (Sept. 17, 2015) -- Contractor will be pouring sidewalk and ramps next week in the North Shores addition. They should be finished this coming week.

UPDATE: (Sept. 11, 2015) -- Contractor is removing and pouring on Voyager, Bridgetown Run, and Breakwater. Work on the project should be done very soon and contractor will start looking for final "punch list" items to do before completing the project.

UPDATE: (Sept. 3, 2015) -- Contractor is working on Voyager, Bridgetown Run, Breakwater, Whaler's Run and Iseview. Removing and pouring on various patches.

UPDATE (Aug. 20, 2015) Contractor will be in North Shores on Bridgetown, Breakwater, Leeward Cove, Voyager, and Whalers Run. They will also be working on a few misc ramps on Crystal Springs.

UPDATE: (Aug. 14, 2015) Contractor is working in North Shores on Voyager, Whaler's Cove, Breakwater, Bridgetown Run and should be buttoning up Haverhill on Crystal Springs, and Holly Tree.

UPDATE: (Aug. 7, 2015) The intersection at Winterfield and Aboite Center is once again an OUT only until they are done with that area. Hopefully will be out of that area by end of next week so not to be in the way of the busses for too long. Next week Garcia will be removing and getting areas ready on Winterfield up by Aboite Center. Also pouring and forming areas on Crystal Springs and in North Shores on Breakwater, Bridgetown, and Voyager.

UPDATE: (Week of Aug. 3, 2015) Contractor will be working and pouring new concrete on Leeward Cove, Isleview, Breakwater Dr, Bridgetown Run. They will be removing old concrete later in the week on Crystal Springs, Morning Wind, Winterfield, and Holly Tree. Winterfield and Aboite Center intersection will probably be closed in the next week or so.

UPDATE: (Week of July 27, 2015) Contractor will be pouring new concrete on Winterfield, Sea Wind and Crystal Springs. They'll be removing old concrete on Leeward Cove, Isleview, and Bridgetown Ct in North Shores. Will also remove on Crystal Springs and underdrain will be put in on Leeward and Isle View.

UPDATE: (Week of July 20, 2015) Contractor should be pouring new concrete  on Thunder Hill, Soaring Hill, and Sea Wind. Should be removing roadway on Morning Wind, Crystal Spring, and Holly Tree. The intersection at Aboite Center and Winterfield still remains to be an exit, Work should start on the other side of that entrance next week. 

UPDATE: (Week of July 7, 2015) Contractor will be removing and pouring on Winterfield near Aboite Center. Also working on Sea Wind, Soaring Hill and Thunder HIll, along with the cul de sacs off of Crystal Springs.

UPDATE: (July 1, 2015) Contractor will continue removing old pavement and pouring new pavement on Crystal Springs and the cul de sacs off Crystal Springs, Holly Hill and Locust Spring, and also working on Winterfield. The contractor may have to close the entrance at the end of the week.

*****UPDATE: (June 15, 2015) ** CHANGE IN TRAFFIC PATTERN: At the Intersection od Aboite Center Road and Winterfield, Garcia Concrete (the contractor) will be turning this intersection into a one-way out when they get in that area.THIS SHOULD HAPPEN EITHER ON OR AFTER WEDNESDAY  JUNE 17, 2015. When they do one side of the boulevard, it is too narrow for two cars to use this entrance. Signs will be posted and Haverhill Association will be notified. When they get in this area, it should be approx two weeks before it is open to all traffic.

*****UPDATE: (June 2, 2015) ** CHANGE IN TRAFFIC PATTERN: At the Intersection od Aboite Center Road and Winterfield, Garcia Concrete will be turning this intersection into a one-way in/or out when they get in that area. When they do one side of the boulevard, it is too narrow for two cars to use this entrance. This should happen in a few weeks at most. Signs will be posted and Haverhill Association will be notified. When they get in this area, it should be approx two weeks before it is open to all traffic.

UPDATE: (June 2, 2015) Contractor will continue working to remove and pur concrete on Winterfield(south end), Sea Wind Place (both sides of Winterfield), and parts on Woodstream and Binford.

UPDATE: (Nov. 18) NO SALT on new concrete streets & sidewalks! Please be aware that new concrete streets cannot have salt applied to them for the first year after they've been poured. The use of salt will cause new concrete to deteriorate. Snow removal teams are using sand to treat new concrete streets, after snow or ice incidents. Residents are asked to also use sand on new concrete drive approaches and sidewalks.

UPDATE: (Sept. 26) On Monday, Sept. 29, contractors will resume work in the Haverhill area. They will complete work on Houndshill Pl and work on Wolf River Pl and Creek Bed Pl.

UPDATE: (Aug. 6) Work has been completed on Weatherside Run & on half of Houndshill Pl. Work is starting on Wolf River Pl & nearby area. Next: Contractor will head West to Plantations of Aboite & Aboite Lake Estates.

Parking: Residents may not have access to their driveway while work is being done on the section of their street. Please park away from construction and DO NOT block traffic lanes.

Trash & Recycling Collection: The night before collection day, residents should place their garbage and recycling containers near the curb, away from the barricades of construction zones for collection – which may be across the street or at the end of the cul-de-sac.

If garbage collection trucks are not able to get to your street, due to construction work, they will try to collect the next day, before construction begins in the morning. For more information, call 311.

Neighborhood Engagement: Public Works staff members have been meeting with neighborhood associations to give residents the opportunity to view work zones, meet the contractors and ask questions about work being done in their neighborhoods. For questions or concerns, you may reach the Division of Public Works by calling 311 or 427-8311.

Warning: PLEASE DO NOT move barricades placed by the contractor, in an attempt to get into your driveway or down the road. A road that "looks" dry -- but is still barricaded -- is NOT complete. It takes 7 to 14 days for proper cure of cement concrete pavement and drive approaches. If this curing time is not given, and vehicles are driven on the new road, the concrete repair will NOT last and road quality will be comprised!!!!