Investing in our Neighborhoods

ARLINGTON PARK -- Phase 1

Contractor: Hipskind Concrete
Start date:  Week of May 23, 2016
Completion Date: April 2017
Investment: $3.08 million

This is the first phase of a 3-phase project.

Improvements include concrete spot repair and reconstruction of concrete streets and affected drive approaches in the Arlington Park neighborhood.

Improvement work also includes repair and replacement of some sidewalks and updating ADA (Americans with Disabilities Act) sidewalk curb ramps.

ArlingtonDONE

 

UPDATES:

April, 2017: Contractor worked to complete sidewalk, do back filling and hydro-seeding.

March 20, 2017 -- Contractor removed sidewalk on Roanoke.

Jan. 4, 2017 -- All street patchwork is done.

November- December 2016 -- Middle lane of West Arlington Pk. Blvd. and N. Arlington Pkw should be done by Thursday, Nov. 3., Hartford is done, as of Nov. 10. Roanoke is done, as of Nov.10.  Potomac is 90% done, as of Nov.14.  North Arlington Parkway is done, as of  Dec.8.

UPDATE: For safety reasons,  Potomac/Roanoke will, temporarily, become a ONE-WAY street, beginning on Tuesday, Oct. 4, 2016. This change in traffic pattern will last as long as needed.

UPDATE: Sept. 26, 2016 -- East side of Hartford,North of Frontier was poured. Next, contractor will be removing the outside of W. Arlington Pkwy all the way around

UPDATE: Sept. 14, 2016 -- Contractor is stoning and pouring South side of Sagimore West , Stoning Quincy East. South side of Frontier was poured, The East side Hartford was removed.

UPDATE: Sept. 8, 2016 -- Contractor is working on Hartford- Frontier to CUL-DE-SAK, Potomac- N. Arlington Pkwy to Tewksbury. Contractor completed removal of N.S. of Quincy East and Montcalm is done. 

UPDATE:  Sept. 1, 2016 -- Planning to remove pavement on Sagimore West, Next in line would be Quincy East. West Arlington Pk. Contractor poured South side of Tewksbury West , Greenwich East. Removed South Side of Frontier.

UPDATE: Sept. 1, 2016 -- Conbtractor poured new pavement on South side of Tewksbury West and Greenwich East.  Also, removed pavement on South Side of Frontier

UPDATE:  Aug. 12, 2016 -- Back filling and top soil on finished streets.

UPDATE: Aug. 11, 2016 -- Finnishing Quincy Ct. West and South side of Greenwich Ct. East

UPDATE:  Aug. 4, 2016 -- Work on Raleigh Ct., Talmage Ct., Albany Ct.,Willowwood Ct., has been finished.  Tewksbury East, Greenwich West, North side of Quincy West has been finished.

UPDATE: July 25, 2016 -- Contractor is working on Sagimore Ct., Tewksbury Ct.

UPDATE: July 22, 2016 -- Contractors has finished work on Raleigh Ct., Talmage Ct., Albany Ct.,Willowwood Ct., Finished

July 7, 2016 -- Contractor poured west side Raleigh, west side Talmage, South side of Sagimore East,South side of Tewksbury East,North side of Greenwich West.

UPDATE: June 16 -- Contractor will be removing east side of Hartford, pouring East side of Albany Ct

UPDATE: June 15 -- Contractor removed west side Raleigh Ct and west Side Talmage, South Side of E. Sagimore Ct.

UPDATE: June 10 -- West side of Hartford is poured South of Frontier, East half of Willowwood Ct is poured.

June 3 - 4. 2016: The plan is to finish removing, Stone and Form on Willowwood Court on Sautrday, June 4.  Next week, the contractor plans to start pouring concrete on Hartford.

UPDATE June 3, 2016: Contractor Hipskind is Forming Hartford TODAY , and placing Geogrid and Stone

UPDATE:  May 25, 2016: Contractor started removing concrete on south end of Hartford Drive, west side.  Next, contractor will begin removing concrete on Albany Ct., Willowood Ct.

UPDATE (Week of May 23): Contractor has begun work on Phase 1. 

UPDATE: A neighborhood meeting -- a Meet the Contractor meeting -- was held April 14, 2016. Contractor announced that construction will begin after May 21-22, which is the weekend of the Annual Arlington Park Neighborhood Garage Sale.

PLEASE DO NOT MOVE BARRICADES

Newly poured concrete needs 7 days to cure. Do NOT move barricades and drive over concrete that is curing. It can damage the concrete, reduce the pavement’s life  -- causing it to crumble within months. Please be vigilant and stop people from moving barricades.

Parking: Residents may not have access to their driveway while work is being done on the section of their street. Please park away from construction and DO NOT block traffic lanes.

Trash & Recycling Collection: The night before collection day, residents should place their garbage and recycling containers near the curb, away from the barricades of construction zones for collection – which may be across the street or at the end of the cul-de-sac.

If garbage collection trucks are not able to get to your street, due to construction work, they will try to collect the next day, before construction begins in the morning. For more information, call 311.

Neighborhood Engagement: Public Works staff members have been meeting with neighborhood associations to give residents the opportunity to view work zones, meet the contractors and ask questions about work being done in their neighborhoods. For questions or concerns, you may reach the Division of Public Works by calling 311 or 427-8311.