Investing in our Neighborhoods

MAYSVILLE ROAD ENHANCEMENT

Contractors: Brooks Construction and S & S Directional
Start date:  Spring 2018
Completion Date: End of 2018
Investment:  5.8 million

Description: This project involves the widening of roadway from 2-lane to 4-lanes, with center turn, from Stellhorn Road to Meijer Drive. It also includes improved sidewalk on east side and trail on west side, two pedestrain bridges, storm sewers, water main and sanitary sewer.

 

3 FINAL LOOKING NORTH AT BRIDGE   4 FINAL LOOKING SOUTH ON MAYSVILLE

 

PROJECT UPDATES

November 26-30, 2018: Crews were unable to pave due to rain leaving the road too wet, workers performed signal and electrical prep work

November 19-21, 2018: Wood fence installed for the pedestrian bridge

November 12-16, 2018: Contractors worked on wiring the light pole bases, crosswalks and signals. Posts were set for the wood fence to be installed at the pedestrian bridge

November 5-9, 2018: Milling continued on Maysville and Stellhorn Rd. pedestrian crosswalk poll was installed in the center median of Maysville Rd. at Meijer Dr and at the corner of Maysville & Stellhorn Rd.

October 29 – November 2, 2018: Crews began milling in both the southbound and northbound lanes on Maysville Rd. Road sign installation continued on Maysville and Stellhorn Rd. and dirt and top soil was added to the center median

October 22-26, 2018: Brooks Construction worked on pavement removal for the center median and continued pouring sidewalk and curb. Top soil was touched up along Maysville Road

October 15-19, 2018: Crews had a busy week as they poured sidewalk on the east and west sides of Maysville Road and the southwest corner of Maysville Road and Stellhorn Road. Installation of street signs began on the west side of Maysville and in the center median. Street Light poles were installed on the east side of Maysville, while the poles on the west side were wired. Concrete curbing was poured over the bridge deck and at several drive approaches .Traffic was switched to the outside lanes to allow crews to focus on the center median between the north side of Koester Ditch, up to Meijer Drive.

October 8-12, 2018: Brooks poured the center island in the commercial drive approach on the west side of Maysville Rd. and sidewalk on the west side of Maysville leading to church. ADA ramps poured on the west side of Maysville Rd., on the south side of Stellhorn Rd and on the northwest corner of Maysville and Stellhorn Rd.

October 1-5, 2018: The contractor placed top soil in the center medians and poured ADA ramps on the west side of Maysville Rd.

September 24-28, 2018: Light poles went up at several locations on the west side of Maysville

September 17-21, 2018:  Brooks Construction finished the curb on the center island and began paving on Maysville and portions of the trail. Crews also brought in topsoil and prepped for landscaping

September 10-14, 2018: Crews prepped for asphalt along the curb line on the west side of Maysville Rd. and poured curb for the center median as another crew poured concrete for new light pole bases.

September 4-7, 2018: Curbing poured on the west side of Maysville Rd

August 27-31, 2018: Brooks Construction poured new curbing on the south side of Stellhorn Road in the beginning of the week and moved to the north side curbs at the end of the week. Dry weather allowed for debris removal and power washing of the west pedestrian bridge.  Crews prepped and poured the bridge deck rail on the west side of Maysville Rd.

August 20-24, 2018: Work on the pedestrian bridge and drive approaches commenced when possible in between bouts of rain

August 13-17, 2018: Contractors continued with prepping for the pouring of concrete, new street light poles were installed on the east side of Maysville and drain tile placed on the west side.  Crews were able to clear debris from the north and south sides of the bridge approaches before rain and storms arrived at the end of the week.

August 2018:  Crews preparing southbound lanes and west side for pouring of sidewalks and roadway

July 2018:  Both pedestrian bridges were delivered and set in place, sidewalk poured, surface paved and guard rail installed on the east side of Maysville.  Traffic switched to the east side on 7-27-18.

June 2018: Curb along east side of Maysville Rd. completed, east side of bridge and drive approaches poured

March - May 2018:  Work completed on sewer, sanitary, storm and water lines

February 2018:  Clearing of right of way

PLEASE DO NOT MOVE BARRICADES

Newly poured concrete needs 7 days to cure. Do NOT move barricades and drive over concrete that is curing. It can damage the concrete, reduce the pavement’s life  -- causing it to crumble within months. Please be vigilant and stop people from moving barricades.

Parking: Residents may not have access to their driveway while work is being done on the section of their street. Please park away from construction and DO NOT block traffic lanes.

Trash & Recycling Collection: The night before collection day, residents should place their garbage and recycling containers near the curb, away from the barricades of construction zones for collection – which may be across the street or at the end of the cul-de-sac.

If garbage collection trucks are not able to get to your street, due to construction work, they will try to collect the next day, before construction begins in the morning. For more information, call 311.

Neighborhood Engagement: Public Works staff members have been meeting with neighborhood associations to give residents the opportunity to view work zones, meet the contractors and ask questions about work being done in their neighborhoods. For questions or concerns, you may reach the Division of Public Works by calling 311 or 427-8311.