Investing in our Neighborhoods

PINE VALLEY/WINDRIFT – Phase 1

Contractor: Garcia Concrete
Start date:  Late September 2016
Completion Date: November 2017
Investment: $2.87 million

 Description: This project involves spot repair, reconstruction of concrete streets & sidewalks and storm drainage improvements in the Pine Valley and Windrift
neighborhoods. It will also include affected drive approaches & curb ramps.

Map

There will be a Phase 2 of the Pine Valley-Windrift neighborhood improvement plan. Designs for Phase 2 are being finalized. More details will be released in 2017.

 A Neighborhood Meeting  for Phase 1 was held on Sept. 7, 2016 at 6 p.m., at the Pine Valley Country Club. The event included presentations by Garcia Concrete, general contractor, API, contractor; Mario Trevino, Traffic Engineering Manager; Greg McDermit, project manager; Andi Adams, City Utilities Construction Manager; Kathleen Herber and Ron Sheppard, City Utilities; Kira Blacketor, Solid Waste and Karen Davis, Public Works.

 PineValleyBefore

 UPDATES:

Dec. 5, 2017 -- Contractor Garcia plans on removing walk on Willow cove and Willowind Trail. 

Week of Nov. 27, 2017 -- Contractor Garcia plans on pouring the rest of Westwind Dr. (southbound by AEP easement)  on 11/27.
Garcia plans on putting K drain in on the eastside of Willow Cove and removing last section of Candlewood Way(eastbound) from Coldwater to drive approach at apartments on 11/28.
Garcia plans on pouring the rest of Willow Cove and continuing backfilling tomorrow and Friday.  They also plan on placing under drain on Candlewood Way and prepping subgrade for final pour next week on Thursday, 11/30.

Week of Nov. 20 - 22, 2017 -- Contractor Garcia plans on pouring approaches on Willow Cove, Seamist, sidewalk on Westwind Pl and Westwind, and Shalimar at Pencross.

Early November 2017 -- Contractor Garcia plans on setting structures on Seamist and pouring patches and Garcia plans on removing pavement on Willow Cove and putting K drain in. (southbound) on November 3.
Contractor Garcia plans on cutting grade on Westwind Dr.(west side) and  forming Candlewood (westbound) on November 15.

Oct. 31, 2017 -- Garcia poured 180 yards on Candlewood (westbound) and is in the process of removing pavement on Seamist and placing subbase.

Week of Oct. 23, 2017 -- Contractor Garcia poured pavement east of Westwind at Candlewood. On 10/26, began Garcia removing pavement on Willowind.

Week of Oct. 16, 2017 -- Contractor Garcia poured street on Westwind Place and cut grade on Westwind Drive, northbound lane, south of Clarion to AEP easement.

Week  of Oct. 9 -- Contractor Garcia started removing pavement on Westwind Place (north side of the road.) Garcia begins pouring approaches on Cove Crest.

Week of Sept. 25 -- Contractor Garcia poured 200' on Westwind Dr. in the southbound lane just north of the bridge and sidewalk and approaches on Seamist on 9/25. Proof roll passed on Cove Crest. Garcia plans on prepping and pouring Westwind Drive from bridge to Willowind (southbound lane, starting on the south end) 9/25

TRAFFIC ALERT: Garcia will make Candlewood Way a one way for eastbound traffic starting on Tuesday, Sept. 26th

Garcia plans on pouring the rest of the southbound lane of Westwind Drive from Willowind Trail to 200' north of the bridge on 9/26.

Week of Sept. 18 -- Garcia proof-rolled Westwind Drive from bridge to Willowind and had to undercut and place winfab on 300+ feet in the southbound lane. Garcia also finished cutting grade on northbound lane of Cove Crest on 9/22.

Week of Sept. 11 -- Contractor Garcia poured the rest of Cove Crest (southbound) on 9/12. Garcia's removal crew finished west and southbound lanes on Seamist and are prepping areas with stone, 9/12.


Week of Sept. 4 -- Contractor Garcia poured pavement on Westwind Drive (northbound) from bridge to 200' north, 9/5. Contractor is also removing pavement on Cove Crest (southbound) on 9/5.  Contractor Garcia stoned and formed Cove Crest on 9/7/ Garcia plans on removing pavement on Seamist Pl. and stoning areas on 9/8.

Aug. 28, 2017 -- Contractor Garcia poured sidewalk on Waycliffe.

Week of  Aug. 23 - 25: Garcia poured 70 yards of concrete on S/W Cor. of Candlewood Way and Westwind Dr. 8/23. Garcia started removing sidewalk on Waycliffe 8/23. 

Week of Aug. 14 - 18:  Contractor Garcia pouring pavement on Westwind Drive (Northbound Lane) south of Willowind Drive and removing pavement on Clarion Drive (Eastbound Lane) towards Trails End, 8/14. Garcia proof-rolled Clarion (eastbound lane up to Trail End) and placed sub-base, 8/16.
Garcia removed  pavement on Candlewood and Westwind Dr., (eastbound lane,) 8/17.

Week of Aug. 7 - Aug. 11:  Contractor Garcia placed underdrain in on east side of Westwind Drive from Willowind Trail to 800' South on 8/8. Garcia cutting grade and under cutting area where proof roll failed 150' South of intersection of Willowind Trail on 8/9.

Week of July 31 - Aug. 4:  Contractor Garcia removing northbound lane on Westwind Drive, north of Westwind Place on 8/3.

July 26, 2017 -- Contractor Garcia began  forms on Clarion from Trail End to west. Garcia began removing walk on Willowind between Harbour Pointe and Westwind Drive.

July 24, 2017 -- Contractor Garcia plans on placing 6" under drain from inlet at S/E corner of Westwind Drive and Clarion. Garcia finished south half of Westwind Place.

July 21, 2017 -- Contractor Garcia began removing pavement & cutting grade westbound on Clarion from Trail End.

July 11, 2017 -- Contractor Garcia poured street on Clarion going east to first structure (north side). They also poured drive approach at #11209 Clarion and curb ramps at Pencross and Shalimar (north / south).

July 6 2017 -- Contractor Garcia poured westbound Clarion from existing structures to west. And, Garcia began cutting grade and forming sidewalk on Westwind Drive (east side) by Westwind Ct.

June 27-29, 2017 -- Contractor Garcia poured sidewalk on Shalimar(east side,) north of Pencross, and Garcia poured sidewalk and approaches on Breton and Pencross.  Also, Garcia poured four patches on Westwind south of Pencross.

June 21, 2017 --  Contractor Garcia poured pavement patches on Shalimar north of Pencross on west side. And, Garcia began removing pavement on Westwind (east side) south of Westind Ct. Also, Garcia began forming curb ramp corners on Shalimar and Pencross.

June 19, 2017 -- Contractor Garcia plans on removing pavement on Westwind Place (eastbound).

Week of June 12 - 16 -- Contractor Garcia started backfilling Chaplewood, Driftwood, Orchard, Wellingham, Willowind Tr., Willowind Ct., Harbour Pt. on 6/12.  Also, Garcia removed 100' of northbound pavement on Westwind/Wingate and poured pavement on Willowind-south side of road from Willowind Ct. to Harbour Pt.

Contractor Garcia poured N/E intersection of Westwind and Clarion. On, 6/14/17, Garcia began excavating for new 2x3 structure on north side of Pencross. On 6/16/17, Garcia poured approaches and walk on Shalimar, south of Pencross.

June 7, 2017 -- Contractor Garcia pouring pavement on Pencross and Shalimar. Garcia also plans on pouring sidewalk and approaches on Wingate (south side) 6/7/17.

June 6, 2017 -- Contractor Garcia placed 6" underdrain on east side of Westwind from structure south of bridge to south around corner on Clarion. We moved drain tile back at corner because of an existing 12"cmp in way.

June 5, 2017 -- Contractor Garcia removed pavement on Westwind and Clarion. And, Garcia also poured sidewalk on Westwind Court.

May 30- 31, 2017 -- Contractor Garcia removed sidewalk on Westwind Ct. And, Garcia poured intersection at Breton and Shalimar.

May 26, 2017 -- Garcia planned on removing pavement on Shalimar, north of Pencross.

May 22, 2017 --  Contractor Garcia began removing 4' curb on Willowind on south side from Orchard Ln. to Wellingham Ct.

Garcia planned on placing under-drain in on south side of Willowind Lane, from Orchard Ln. to Wellingham Ct.

May 19, 2017 -- Westwind Ct., Intersection of Breton and Shalimar (N/E), and 60' section on northbound Shalimar between Breton and Pencross are formed and read to pour.

May 15, 2017 -- Contractor Garcia opened south 1/2 of Westwind Ct. and will begin removing pavement on the north side.

May 12, 2017 -- Contractor Garcia plans on pouring sidewalk on north side of Wingate. 

May 11, 2017 -- Contractor Garcia poured 4'-wide curb on Willowind Trail. Contractor is also removing pavement on Wingate.

May 8, 2017 -- Contractor Garcia poured on Shalimar and Pencross intersection and 160' on Pencross. And, contractor also removed pavement on Breton.

May 1, 2017 -- Contractor Garcia poured section of pavement on Shalimar south of Breton

April 17-28, 2017 -- Contractor Garcia poured pavement on Willingham (4/24) and began pouring east side of Shalimar (4/26).

April 3, 2017 -- Contractor Garcia poured concrete pavement on Orchard and Willowind.

March 29- 31, 2017 -- Contractor Garcia poured sidewalk and approach on east side of Driftwood Pointe and sidewalk on Wellingham Ct.

Dec.. 12, 2016 -- Garcia began removing sidewalk on Orchard Place and Wellingham and concrete pavement on Chaplewood

Nov. 29, 2016 - - Contractor Garcia began pouring concrete pavement on Shalimar

Nov. 25, 2016 -- Contractor API started sewer drainage work on Westwind Ct. and Westwind Dr. and finished laying pipe on Westwind on 12/6/2016

Nov. 22, 2016 - -Contractor Garcia removed pavement on Wingate and Shalimar

Nov. 21, 2016 -- Contractor Garcia poured sidewalk on west side of Brandywine and stoned east side of Brandywine at Lochinvar

November 2016 -- Contractor Garcia removed pavement on Wellingham Ct., Willowind Ct. and Orchard Lane. Also, poured concrete and installed ramps on corner of Orchard Place and Willowind

November 2016 -- Contractor API continued laying pipe and repairing pipes on Shalimar and from Ditch behind Clarion Drive.

Oct. 21, 2016 -- Contractor API plans on placing rip-rap along ditch area behind Brandywine (west side)  and pouring inverts in structures.

Oct. 17, 2016 -- Contractor API lowered water main on Brandywine.

Oct. 10, 2016 -- Contractor API is laying larger pipe from ditchline to structure #36 and removing existing 24"cmp 10/10/16

Oct. 4, 2016 -- Contractor API started excavating and placing gabions in ditch area west of Brandywine. 10/4/16

Sept. 29, 2016 -- Contractor plans to begin filling potholes on Brandywine and Lochinvar, setting up equipment on Oct. 1 and then begin construction on Oct. 3.

PLEASE DO NOT MOVE BARRICADES

Newly poured concrete needs 7 days to cure. Do NOT move barricades and drive over concrete that is curing. It can damage the concrete, reduce the pavement’s life  -- causing it to crumble within months. Please be vigilant and stop people from moving barricades.

Parking: Residents may not have access to their driveway while work is being done on the section of their street. Please park away from construction and DO NOT block traffic lanes.

Trash & Recycling Collection: The night before collection day, residents should place their garbage and recycling containers near the curb, away from the barricades of construction zones for collection – which may be across the street or at the end of the cul-de-sac.

If garbage collection trucks are not able to get to your street, due to construction work, they will try to collect the next day, before construction begins in the morning. For more information, call 311.

Neighborhood Engagement: Public Works staff members have been meeting with neighborhood associations to give residents the opportunity to view work zones, meet the contractors and ask questions about work being done in their neighborhoods. For questions or concerns, you may reach the Division of Public Works by calling 311 or 427-8311.