PWlogoweb

Investing in our Neighborhoods

Goshen Avenue Reconstruction 

 

Start Date

July 2019

Estimated Completion Date

October 2020

Contractor

Primco, Inc.

Investment

$5.2 Million

Project Information

 This project involves the reconstruction and modernization of Goshen Avenue from State Boulevard to Cambridge Boulevard. It includes the conversion of the Five Points intersection to a roundabout, repair of existing sidewalk & curb ramps, the addition of new sidewalks and ADA curb ramps, landscaping, improved drainage, new street lights and signalized intersection improvements
Project Renderings (click the links to view)Goshen_1Goshen_2  Goshen_3 
Goshen_4   
Goshen_5 pdfGoshen_6  pdfGoshen_7
 
 
September 3, 2019 

Fiber relocation and widening on the south side of Goshen Rd for a temporary lane is complete, crews plan on starting storm sewer wrok on the west end of Goshen

August 1, 2019 

Groundbreaking Ceremony scheduled for today

July 23, 2019 

Survey work completed, traffic control to be installed in preparation of construction that will begin in a few weeks

July 19, 2019 

Primco has started their survey work on Goshen Ave  from Cambridge to State. As of yet there are no barricades or traffic control on Goshen but motorists may see some work beginning out there. Work beyond the survey is expected in the next week or two.

Public informational meeting scheduled for July 11, 2019 - click the link to download more information    pdfGoshen Avenue - Meet The Contractor
June 26, 2019 

Project awarded to Primco, Inc. on 6/11/19 - construction start date to be determined when the pre-construction meeting is held and the schedule is finalized

June 6, 2019Received contractor bids on June 4, 2019, information will be updated when project is awarded
May 2019Design work completed and project advertised for bid
April 2019Project design 50% complete
March 2019Engineers working on plan submittals and utility coordination

 

PLEASE DO NOT MOVE BARRICADES

Newly poured concrete needs 7 days to cure. Do NOT move barricades and drive over concrete that is curing. It can damage the concrete, reduce the pavement’s life  -- causing it to crumble within months. Please be vigilant and stop people from moving barricades.

Parking: Residents may not have access to their driveway while work is being done on the section of their street. Please park away from construction and DO NOT block traffic lanes.

Trash & Recycling Collection: The night before collection day, residents should place their garbage and recycling containers near the curb, away from the barricades of construction zones for collection – which may be across the street or at the end of the cul-de-sac.

If garbage collection trucks are not able to get to your street, due to construction work, they will try to collect the next day, before construction begins in the morning. For more information, call 311.

Neighborhood Engagement: Public Works staff members have been meeting with neighborhood associations to give residents the opportunity to view work zones, meet the contractors and ask questions about work being done in their neighborhoods. For questions or concerns, you may reach the Division of Public Works by calling 311 or 427-8311.