Investing in our Neighborhoods

PINE VALLEY/WINDRIFT – Phase II       

Frank Pine2

 

 

 

 

 

 

 

Contractor: Hipskind Concrete
Start date:  Spring 2018
Completion Date:  May 2019
Investment: $2,871,000.00

Description: This project involves spot repair, reconstruction of concrete streets & sidewalks and storm drainage improvements in the Pine Valley and Windrift neighborhoods. It will also include affected drive approaches & curb ramps. This is the second phase of improvement work being done in these two neighborhoods. 

 

December 10, 2018 - The construction phase of the project is substantially complete, Hipskind plans backfill and lay topsoil to restore all locations this week.

December 3-7 - Contractor removed drive approaches on Kings Crossing between Old Lantern and Ransom, removed and poured sidewalk on Trails North.  Driveway approaches poured on the west side of Kings Crossing between Ransom and Old Lantern.  Ramps poured at Jewel Ct. and Colony Ct. and at Ransom (south side of Kings Crossing) Workers began backfilling.

November 26-30 - Hipskind removed pavement on Ransom in the westbound lane between Wayfair and Ransom Ct., pavement and drive approaches removed on Trails North in the southbound lane between Trails End and Colony Ct. Pavement poured on Kings Crossing and Trails North, as well as drive approaches and sidewalk on the west side of Trails North between Trails End and Colony Ct.

November 19-21, 2018 - Hipskind poured pavement on Trails North, ramps at the corners of Trails North and Trails End ; Kings Crossing and Ransom ; Ransom Ct. and Ransom ; and on the east side of Trails North across from Colony Ct.

November 12-16, 2018 - Pavement poured on Ransom, Trails North. Drive approaches poured on Kings Crossing as well as a ramp at the southeast corner of Ransom and Ransom Ct. Underdrain installed on Trails North in the southbound lane between Colony Ct. and Kings Crossing and on Kings Crossing in the southbound lane between Old Lantern and Ransom. Hipskind removed pavement on Kings Crossing between Old Lantern and Ransom in the southbound lane.

November 5-9, 2018 - Hipskind removed pavement on Trails North in the southbound lane between Colony Ct. and Kings Crossing, Kings Crossing from Ransom Drive to Old Lantern, Trails North between Kings Crossing and Colony Court in the southbound lane.  Contractor  prepped Ransom Drive from Auburn Road to Wayfair

October 29- November 2, 2018 -  Pavement removed eastbound lane of Ransom between Wayfair and Auburn, Trails North between Colony Ct. and Trails End in southbound lane. Contractor installed underdrain on Kings Crossing between Ransom and Old Lantern in the westbound lane. Pavement poured on Kings Crossing and Trails North. Drive approaches poured on Ransom 

October 24-26, 2018 - Pavement poured on Trails North and continued on Ransom Dr. drive approaches & ramps removed on Ransom. Ramp poured at the corner of Kings Crossing & Trails North. Ramps poured at the NE & NW corners of Wayfair & Ransom.Backfilled on Ransom behind curbs

October 23, 2018 - Hipskind pouring pavement on Ransom.

October 22, 2018 - Contractor removed pavement on Kings Crossing, northbound lane between Ransom and Old Lantern.  Hipskind backfilled and topsoiled on Trails North and Old Lantern

October 15-19, 2018 - Pavement removed on Ransom Dr. between Canter and Kings Crossing and on Kings Crossing between Old Lantern and Ransom Dr. Contractors placed underdrain on Ransom and Trails North before  pouring pavement on Ransom and drive approaches on Trails North.

October 8-12, 2018 - Contractor continues to remove northbound pavement on Trails North between Trails End and Kings Crossing  All sidewalks and ADA ramps now completed in Windrift

October 1-5, 2018 - Hipskind removed pavement on Ransom Ct. and Trails North.  Underdrain was installed on Old Lantern and Trails North.New pavement poured on Windrift and Old Lantern.  Crews poured sidewalks on Windrift, Glen Eagle and Grand River as well as approaches on Ransom.  New pavement placed on Windrift Ln.

September 24-28, 2018 - Pavement removed on Ransom Dr., Old Lantern and Trails North. Underdrain installed on Windrift Ln and Trails North. Sidewalks and approaches excavated and poured on Kings Crossing, Trails North, and Windrift. Contractor poured pavement on Ransom.   

September 24, 2018 - The contractor plans to pour pavement on Ransom Drive early this week

September 18-21, 2018 - Hipskind poured pavement on Trails North, Kings Crossing and approaches on Windrift, Grand River and Ransom. Pavement was removed and underdrain installed on Ransom in the westbound lane between Kings Crossing and Canter.  Crews installed ADA ramps at the northeast and northwest corners of Old Lantern/Lantern and began restoration of grass seed and top soil on Old Colony

September 17, 2018 - The contractor plans to pour pavement on Kings Crossing from Trails North to Ransom Dr. and on Ransom Dr. from Kings Crossing to Canter this week

September 11-14, 2018 - Crews poured pavement on Ransom Ct., Trails North and Old Lantern.  Sidewalks and/or drive approaches on  Old Lantern, Ransom, Glen Eagle Way and Wayfair.  Pavement removed on Ransom between Kings Crossing and Canter in the westbound lane.  Underdrain installed on Kings Crossing     

September 11, 2018 - Barring any unforeseen circumstances, the contractor plans to pour pavement at the intersection of Wayfair and Ransom today and southbound Ransom Ct. on Wednesday

September 7, 2018 - Hipskind removed drive approaches and sidewalk on Wayfair, pavement on Old Lantern and Kings Crossing

September 6, 2018 - Pavement poured on Windrift Ln while crews continued removal of old surface on Old Lantern, Trails North and Wayfair

September 5, 2018 - Pavement poured on Windrift Ln, pavement removed on Trails North and Kings Crossing

September 4, 2018 - Crews working on pouring pavement on Carriage Pl., removing  pavement in the southbound lane on Ransom Ct., and sidewalk removal on Windrift Lane between Glen Eagle Way and and Grand River Dr.  

August 31, 2018 - Hipskind poured pavement on Old Lantern and approaches on Trails North. Pavement was removed on Ransom Ct. in the southbound lane. 

August 30, 2018 - New pavement poured pavement on Kings Crossing. Pavement was removed and sidewalks poured on Ransom Ct.   

August 29, 2018 - Hipskind installed underdrain on Windrift Ln. between North Star Pl. and Coldwater in the westbound lane and removed pavement on Ransom Ct. in the southbound lane

August 28, 2018 - New pavement poured on Wayfair, sidewalks poured on Ransom.  Excavation of old pavement on Windrift Ln. - westbound lane between Coldwater and Glen Eagle Way.  Hipskind installed underdrian on Windrift Ln. between North Star Pl. and Coldwater Rd.

August 27, 2018 - Construction crews excavated pavement on Windrift Lane - westbound lane from North Star to Coldwater.  Underdrain was installed on Windrift Lane - westbound lane between North Star Pl. and Grand River Dr.

August 20-24, 2018 - Hipskind Concrete began the week pouring pavement on Trails North and new approaches on Carriage. Excavation resumed on Carriage Ct. and Ransom Ct. while new surface was poured on Old Lantern, Trails North as well as approaches on Grand River Dr. and Windrift Lane. Crews finished the week by pouring a considerable amount of new sidewalk on Ransom Drive.

August 13-17, 2018 - Crews installed underdrain on Trails End, Trails North, Wayfair and at the intersection of Kings Crossing and Old Lantern. Old pavement was removed from drive approaches, sidewalks, and from roadway lanes on Wayfair, Kings Crossing, and Ransom. Hipskind replaced sidewalks on Ransom and Trails North and poured drive approaches on Wayfair and Trails End. Pavement removal continued from on Carriage Ct. (northbound lane) along with sidewalk removal on Ransom and Carriage Court.  The week ended with the placement of additional underdrain Wayfair and Kings Crossing.

August 10, 2018 - The week of 8/6 - 8/10 concrete sidewalk was poured on Carriage Place

Hipskind Concrete began construction in March, 2018, starting work on Old Lantern Trail and continuing with the following locations:  Northstar Place, Grand River Dr., Colony Ct., Jewel Ct., Wayfair, Glen Eagle, Windrift, Trails End

 

PLEASE DO NOT MOVE BARRICADES

Newly poured concrete needs 7 days to cure. Do NOT move barricades and drive over concrete that is curing. It can damage the concrete, reduce the pavement’s life  -- causing it to crumble within months. Please be vigilant and stop people from moving barricades.

Parking: Residents may not have access to their driveway while work is being done on the section of their street. Please park away from construction and DO NOT block traffic lanes.

Trash & Recycling Collection: The night before collection day, residents should place their garbage and recycling containers near the curb, away from the barricades of construction zones for collection – which may be across the street or at the end of the cul-de-sac.

If garbage collection trucks are not able to get to your street, due to construction work, they will try to collect the next day, before construction begins in the morning. For more information, call 311.

Neighborhood Engagement: Public Works staff members have been meeting with neighborhood associations to give residents the opportunity to view work zones, meet the contractors and ask questions about work being done in their neighborhoods. For questions or concerns, you may reach the Division of Public Works by calling 311 or 427-8311.