Investing in our Neighborhoods

PINE VALLEY/WINDRIFT – Phase II       

Frank Pine2

 

 

 

 

 

 

 

Contractor: Hipskind Concrete
Start date:  Spring 2018
Completion Date:  May 2019
Investment: $2,871,000.00

Description: This project involves spot repair, reconstruction of concrete streets & sidewalks and storm drainage improvements in the Pine Valley and Windrift neighborhoods. It will also include affected drive approaches & curb ramps. This is the second phase of improvement work being done in these two neighborhoods.

Project Update:

Hipskind Concrete began construction in March, 2018, starting work on Old Lantern Trail and continuing with the following locations:  Northstar Place, Grand River Dr., Colony Ct., Jewel Ct., Wayfair, Glen Eagle, Windrift, Trails End

August 10, 2018 - The week of 8/6 - 8/10 concrete sidewalk was poured on Carriage Place

August 13-17, 2018 - Crews installed underdrain on Trails End, Trails North, Wayfair and at the intersection of Kings Crossing and Old Lantern. Old pavement was removed from drive approaches, sidewalks, and from roadway lanes on Wayfair, Kings Crossing, and Ransom. Hipskind replaced sidewalks on Ransom and Trails North and poured drive approaches on Wayfair and Trails End. Pavement removal continued from on Carriage Ct. (northbound lane) along with sidewalk removal on Ransom and Carriage Court.  The week ended with the placement of additional underdrain Wayfair and Kings Crossing.

August 20-24, 2018 - Hipskind Concrete began the week pouring pavement on Trails North and new approaches on Carriage. Excavation resumed on Carriage Ct. and Ransom Ct. while new surface was poured on Old Lantern, Trails North as well as approaches on Grand River Dr. and Windrift Lane. Crews finished the week by pouring a considerable amount of new sidewalk on Ransom Drive.

August 27, 2018 - Construction crews excavated pavement on Windrift Lane - westbound lane from North Star to Coldwater.  Underdrain was installed on Windrift Lane - westbound lane between North Star Pl. and Grand River Dr.

August 28, 2018 - New pavement poured on Wayfair, sidewalks poured on Ransom.  Excavation of old pavement on Windrift Ln. - westbound lane between Coldwater and Glen Eagle Way.  Hipskind installed underdrian on Windrift Ln. between North Star Pl. and Coldwater Rd.

August 29, 2018Hipskind installed underdrain on Windrift Ln. between North Star Pl. and Coldwater in the westbound lane and removed pavement on Ransom Ct. in the southbound lane.  

August 30, 2018 - New pavement poured pavement on Kings Crossing. Pavement was removed and sidewalks poured on Ransom Ct.   

August 31, 2018 - Hipskind poured pavement on Old Lantern and approaches on Trails North. Pavement was removed on Ransom Ct. in the southbound lane. 

September 4, 2018 - Crews working on pouring pavement on Carriage Pl., removing  pavement in the southbound lane on Ransom Ct., and sidewalk removal on Windrift Lane between Glen Eagle Way and and Grand River Dr.  

September 5, 2018 - Pavement poured on Windrift Ln, pavement removed on Trails North and Kings Crossing
 
September 6, 2018 - Pavement poured on Windrift Ln while crews continued removal of old surface on Old Lantern, Trails North and Wayfair
 
September 7, 2018 - Hipskind removed drive approaches and sidewalk on Wayfair, pavement on Old Lantern and Kings Crossing
 
September 11, 2018 - Barring any unforeseen circumstances, the contractor plans to pour pavement at the intersection of Wayfair and Ransom today and southbound Ransom Ct. on Wednesday
 
September 11-14, 2018 - Crews poured pavement on Ransom Ct., Trails North and Old Lantern.  Sidewalks and/or drive approaches on  Old Lantern, Ransom, Glen Eagle Way and Wayfair.  Pavement removed on Ransom between Kings Crossing and Canter in the westbound lane.  Underdrain installed on Kings Crossing.  
 
September 17, 2018 - The contractor plans to pour pavement on Kings Crossing from Trails North to Ransom Dr. and on Ransom Dr. from Kings Crossing to Canter this week


PLEASE DO NOT MOVE BARRICADES

Newly poured concrete needs 7 days to cure. Do NOT move barricades and drive over concrete that is curing. It can damage the concrete, reduce the pavement’s life  -- causing it to crumble within months. Please be vigilant and stop people from moving barricades.

Parking: Residents may not have access to their driveway while work is being done on the section of their street. Please park away from construction and DO NOT block traffic lanes.

Trash & Recycling Collection: The night before collection day, residents should place their garbage and recycling containers near the curb, away from the barricades of construction zones for collection – which may be across the street or at the end of the cul-de-sac.

If garbage collection trucks are not able to get to your street, due to construction work, they will try to collect the next day, before construction begins in the morning. For more information, call 311.

Neighborhood Engagement: Public Works staff members have been meeting with neighborhood associations to give residents the opportunity to view work zones, meet the contractors and ask questions about work being done in their neighborhoods. For questions or concerns, you may reach the Division of Public Works by calling 311 or 427-8311.