Investing in our Neighborhoods

DUPONT ROAD

Email a Question: This email address is being protected from spambots. You need JavaScript enabled to view it.   

pdfClick here to see and zoom in on a project aerial   

Detour Map

New Aerial video: June 28 Full Length of RoadJune 28 Close UnderpassJune 28 looking east,  

Previous Aerial Video: June 14 Low Angle over underpassJune 14 Pan of Trail Underpass, June 14 heading west, June 14 looking through underpassHigh view of underpassMay 28 wide shot Aerial, May 28 CU of Underpass Wall May 6 Aerial Looking West

Project Update:

  • July 13, 2018 -- The road is taking on an updated look.  Underpass work is looking more and more like the artist renderings, concrete sidewalks were poured this week near Casa Grille.  Asphalt paving is underway in the eastbound lanes from Dawsons Creek to Dupont Village.  Water pipe installation continues. (6 new photos below)
  • July 6, 2018 -- Work continues on the placement of new stormwater infrastructure. New waterline placement is approaching completion near Dawsons Creek. REMC bored under the road to place former overhead lines underground, near La Cabreah. Curbs were placed on the south side from Dupont Village to Dawsons Creek. Cub and drive approach work was completed at Maple Seed Farm. Subgrading of the road over the trail continues.

Click for May-June Updates

Click for Earlier Updates
 

Description: Expanding the road to 4-lanes with a turn lane, where needed; a sidewalk on the north side and a trail on the south side of the road. A below-grade pedestrian/bicycle crossing will connect the Pufferbelly Trail under the road near Salomon Farm Park. Click Project Renderings

Contractor Phend & Brown, Inc. Completion Date:  November 2019  Investment: $12 million

IMG 6553 IMG 6562 IMG 6563 IMG 6565 road construcion concrete work