Investing in our Neighborhoods


Email a Question: This email address is being protected from spambots. You need JavaScript enabled to view it.

Contractor Phend & Brown, Inc. Completion Date:  November 2019  Investment: $12 million

Description:Expanding road to 4-lanes with a turn lane, where needed; a sidewalk on the north side and a trail on the south side of the road. A below-grade pedestrian/bicycle crossing will connect the Pufferbelly Trail under the road near Salomon Farm Park.Click Project Renderings

Project Update:

  • March 16, 2018 --  Utility relocation work continues and construction signage is prepared to move traffic to the southside of the road.  The road will still maintain traffic with one lane in each direction -- but their will likely move slower than normal. (new photos below)
  • It Week of February 26, 2018  Crews cleared brush most of the week in preparation for construction.   Utility crews continued relocation efforts.
  • Week of February 19, 2018 Heavy rain halted this week’s planned brush clearing. The project area is marked for utilities and the gas line relocation work is moving forward. Brush clearing should begin next week.
  • Week of February 5, 2018
    • Frontier, NIPSCO and REMC continue relocation of utility service lines.
    • Crews begin placing road signage for traffic control  and placing the stakes that mark project right-of-way.  The process should be completed by the end of the week.  
  • January 31, 2018 -- More than 150 neighbors turnout for the Meet the Contractor Meeting.

   EB from Nottawa Miller pipeline 2 1ST 48 IN PIPE STR 301