Investing in our Neighborhoods

DEERFIELD ESTATES

Contractor:               Garcia Concrete

Start Date:                September 2018

Completion Date:    June 2019

Investment:              $1,434,435.00

Description:             Project includes spot repair and reconstruction of concrete streets in the Deerfield Estates neighborhood.

 Frank Deer

 

Project Updates:

January 2019 - Garcia Concrete completed work until after the holidays on 12/20/2018, the crews will return to begin installation of underground pipe and structures on Yearling.

December  2018 - Along with continued work on the installation of underground structures, the contractor took advantage of the warmer days, completing the pouring of concrete streets in the west half of the project:  Roe, Buck Ct, Caribou from Buck Ct south and Yearling from Caribou to the cul de sac. 

November 19-21, 2018 - Crews removed concrete on Yearling and poured new surface on Roe, they will continue with concrete work as temperatures allow.  Garcia will focus on installing underground pipes and structures through the winter months when it becomes too cold to pour concrete

November 12-16, 2018 - Garcia poured new concrete on Buck Ct., Caribou Dr. and Roe 

November 5-9, 2018 - Crews began concrete removal on Roe before snow arrived at the end of the week

October 29 - November 2, 2018 - Crews removed concrete and installed underdrain on Buck Ct. 

October 22-26, 2018 - Pouring of concrete continued on Buck Ct.

October 15-19, 2018 - Garcia Concrete poured concrete on Caribou Dr. and Buck Ct.

October 8-12, 2018 - Contractor excavated and placed underdrain on Buck Ct. and poured concrete on Yearling and Caribou.

October 5, 2018 - Construction began on 9/28/18 with crews removing old concrete on Yearling, Caribou and Buck as well as prepping for the underdrain that was placed on Yearling. Pouring of new concrete began on Yearling.  The contractor plans to continue excavating on Buck.

September 17-21, 2018 - Pavement marked for contractor during the week so that crews may begin excavation work next week

September 6, 2018 - Weather permitting, Garcia Concrete hopes to begin construction the week of September 17th.

August 30, 2018:  - Garcia Concrete Construction will begin construction in mid-September.

You can meet the contractor and Public Works project representatives tonight! 

This project involves spot repair or reconstruction of concrete streets;
repair of deteriorated curbs, sidewalks and wing walks and installing ADA curb ramps. 
The majority of the construction will take place in public right-of-way.
We know street repair projects can be disruptive and inconvenient.
We want you to be well-informed about the project and to know who can answer your questions or resolve any construction issues. 
Please join us to meet project representatives from Public Works and Garcia Concrete.
Thursday, August 30th at 6:30 PM - Westview Alliance Church  - 9804 Illinois Road, Fort Wayne, IN  46804
 

PLEASE DO NOT MOVE BARRICADES

Newly poured concrete needs 7 days to cure. Do NOT move barricades and drive over concrete that is curing. It can damage the concrete, reduce the pavement’s life  -- causing it to crumble within months. Please be vigilant and stop people from moving barricades.

Parking: Residents may not have access to their driveway while work is being done on the section of their street. Please park away from construction and DO NOT block traffic lanes.

Trash & Recycling Collection: The night before collection day, residents should place their garbage and recycling containers near the curb, away from the barricades of construction zones for collection – which may be across the street or at the end of the cul-de-sac.

If garbage collection trucks are not able to get to your street, due to construction work, they will try to collect the next day, before construction begins in the morning. For more information, call 311.

Neighborhood Engagement: Public Works staff members have been meeting with neighborhood associations to give residents the opportunity to view work zones, meet the contractors and ask questions about work being done in their neighborhoods. For questions or concerns, you may reach the Division of Public Works by calling 311 or 427-8311.