PWlogoweb

Investing in our Neighborhoods

Edsall Avenue Bridge 

Start Date

November 2018

Estimated Completion Date

August 2019           Actual Completion Date:  9-16-19

Contractor

ICC Group, Inc

Investment

$2 Million

Project Information

Design of new bridge on Edsall Avenue over Norfolk Southern Railroad, from Reynolds to McDonald Street. This project will include approaches and street lighting. 

 
September 2019Project complete, ribbon cutting ceremony held on 9/16/19 and bridge re-opened
August 2019Brooks Construction completed the concrete street and walks
July 2019Approach and intersection pavement removal and prepped for new concrete on  north side of bridge, water valves adjusted 
June 2019Crane was on site the week of 6/17/19 and set all the bridge beams over the railroad. MSE wall caps were framed and poured  
May 2019Contractor prepped the north side for concrete leveling pad,  beams have been extended and the MSE walls are being built on the North and South sides. 
April 2019Crews worked on the south side leveling pad
March 2019Excavation shifts to the south side of the railroad, crane and pilings delivered to begin augering holes
February 2019Contractor resumed work on excavation
December 2018Pavement removal continues on the north side of the birdge
November 2018Contractor began demolition of the bridge with pavement removal on the north side of the bridge and removal of the wood bridge deck 

 

PLEASE DO NOT MOVE BARRICADES

Newly poured concrete needs 7 days to cure. Do NOT move barricades and drive over concrete that is curing. It can damage the concrete, reduce the pavement’s life  -- causing it to crumble within months. Please be vigilant and stop people from moving barricades.

Parking: Residents may not have access to their driveway while work is being done on the section of their street. Please park away from construction and DO NOT block traffic lanes.

Trash & Recycling Collection: The night before collection day, residents should place their garbage and recycling containers near the curb, away from the barricades of construction zones for collection – which may be across the street or at the end of the cul-de-sac.

If garbage collection trucks are not able to get to your street, due to construction work, they will try to collect the next day, before construction begins in the morning. For more information, call 311.

Neighborhood Engagement: Public Works staff members have been meeting with neighborhood associations to give residents the opportunity to view work zones, meet the contractors and ask questions about work being done in their neighborhoods. For questions or concerns, you may reach the Division of Public Works by calling 311 or 427-8311.