Investing in our Neighborhoods 

The Dupont Road Project will expand the road to 4-lanes with a turn lane, where needed. A sidewalk on the north side and a trail on the south side of the road will be added. A below-grade pedestrian/bicycle crossing will connect the Pufferbelly Trail under the road near Salomon Farm Park. Click Project Renderings    Contractor: Phend & Brown, Inc.      Completion Date: November 2019     Investment: $12 million (80% Federal funds, 20% Local funds)
 
Email a Question: This email address is being protected from spambots. You need JavaScript enabled to view it.   

Click video links below shot the week of May 17, 2019: 

May 15, 2019 Dupont Landscaping Aerial,  Aerial Video heading east May 15, 2019

Heading east toward Coldwater April 24, 2019,   Heading west toward Lima April 24 -2019

Archived Videos:

pdfSept - Dec 2018 Aerial Videos

Project Updates

  • May 17, 2019 – Dupont Road is coming to life.  Trees, shrubs and plants are being installed in the median and along the sides of the road.  Recent rains slowed the progress on pouring concrete sidewalks. The project is expected to be completed by the end of the July.  Above you can click on links tfor two new aerial videos.  Scroll down to see four new photos.

  • April 27, 2019 --  Crews continued light pole installation and worked on teh apron entrance at Salomon Farm.  Crews also continued work on the trail and sidewalk portions of the project.  
  • April 19, 2019 --This week crews continued grading and compacting the trail on the south side of the road between Lima and Oak Trail.  Work was performed to widen and improve the entrance Salomon Farm. Lighting crews worked on the north side of the road between Coldwater and LaCabreah and landscaping put in nearly 50 trees.
  • March 21, 2019 -- Works is back in full swing.  Crews were busy removing the temporary winter asphalt.  Lighting installation continued and crews worked on the center island near Coldater at Dupont Village shopping plaza.
  • March 17, 2019 -- Beginning Monday, March 19 -- crews will be removing the temporary asphalt as the move forward to complete the project.  Final paving, landscaping, traffic signals, street lights,and entrance approaches will keep crews busy as they work toward completion of the project. During cunstruction their will be lane restrictions with traffic routed to the two outside lanes through mid April.  There will be delays and lane restrictions from now through the end of the project. 
  • February 21, 2019 -- Work continues though not a the same pace as when the weather is more cooperative.  Snow, ice and bitter cold temperatures have slowed crews, but progress continues.  The new ornamental lighting has arrived and is being installed.  This week aobut 20 of the lights will be in place with approximately another 60 still to go. 
  •   pdfNov - Dec Updates
  • pdfSeptember-October Updates 2018
  • July & August Updates
  • May-June Updates
  • Earlier Updates   
  • MapsAerial Project MapDetour Map

          5 14 Photo showing median PLANTINGS 2 REV  SIDEWALK POUR EAST OF LONE EAGLE Dupont WS Looking E