PWlogoweb

Investing in our Neighborhoods

 

Start Date

Spring 2019 (Actual start date:  March 22, 2019)
Estimated Completion Date September 15, 2019
Contractor Hipskind Concrete
Investment $1.2 million

 

 

Project includes spot repair and reconstruction of concrete streets in the Caribe Colony neighborhood. Improvements also include repair and reconstruction of various curbs and sidewalks as well as the installation of additional ADA (Americans with Disabilities Act) curb ramps.

 

Project Updates:

June 21, 2019 Construction is 90% complete, most of the concrete has been poured with the exception of a few locations, contractor will begin restoration soon
May 27 - 31, 2019 Construction currently 50% complete.
Rainy start to the week, crews are able to resume work on Wednesday, pouring new surface on Martinique and Bimini
May 20 - 24, 2019 Contractor poured concrete street on Bahama Lane, Caribe Blvd., Martinique and Bimini.  Sidewalk poured on Caribe, Martinique and Andros (including curb ramps at the northeast of the intersection of Bahama and Andros and at the southeast of Andros and Martinique).
May 13 -17, 2019 Hipskind continued removal on Nassau, and placement of underdrain on Bimini on the eastern lane heading north towards Martinique, and started placement of underdrain on Nassau in the south lane heading westward from Bimini towards Bahama. Crews continued placement of underdrain starting on Nassau by Bahama and heading towards Bimini.
May 6 -10, 2019 Hipskind removed the NE intersection of Bahama and Andros. Removal continued on Bahama between Andros and Caribe. Sidewalks removed on Andros and on Martinique. Hipskind poured pavement on San Juan Circle and on Caribe 
April 29 - May 3, 2019 Hipskind removed pavement on Caribe between Caribe and Old Maysville in the eastbound lane, drainage laid on Nassau in the westbound lane between Bahama and Caribe and on Caribe from Nassau to Antigua in the northbound lane.  Crews poured pavement on Andros and Martinique.
April 22 - 26, 2019 Hipskind began removal on San Juan Circle
April 15 -19, 2019 Contractor poured sidewalk on Bahama, Bimini, Caribe and Nassau as well as drive approaches  on Martinique.  Pavement removal continued on  Andros in the northbound lane and Martinique in the eastbound lane.  Street poured on Nassau and Caribe
April 8 - 12, 2019

Contractor continuing excavation and grading operations, as well as prepping for underdrain installation on Nassau. along right of way of the project

April 1 - 5, 2019 The contractor removed concrete on Nassau from Bahama heading west in the south lane and began placement of sanitary sewer on Martinique
March 25 - 29, 2019  Crews continue removal of old surface, moving to San Juan Circle and Martinique, as well as prepping for underdrain installation on Martinique
March 22, 2019 Hipskind Concrete began construction with removal of concrete from the southbound lane of Andros Lane

Parking  - PLEASE DO NOT MOVE BARRICADES

Residents may not have access to their driveway while work is being done on the section of their street.
Please park away from construction and DO NOT block traffic lanes. Newly poured concrete needs 7 days to cure. Do NOT move barricades or drive over concrete that is curing.
Vehicle traffic will damage the uncured concrete, resulting in reduced life of the pavement and causing it to crumble within months. Please be vigilant and stop people from moving barricades