Investing in our Neighborhoods

DEERFIELD ESTATES

Contractor:               Garcia Concrete

Start Date:                September 2018

Completion Date:    June 2019

Investment:              $1,434,435.00

Description:             Project includes spot repair and reconstruction of concrete streets in the Deerfield Estates neighborhood.

 Frank Deer

 

PROJECT UPDATES

May 14, 2019

Crews will be finishing up on the south/west side of Stag today. They will be starting to remove at the very south end of  Buckskin, up to Reindeeer and go east on to the addition line. Depending on concrete breaks and weather, after that they should be removing on the east side of Caribou from Illinois to Buckskin, heading east on Buckskin and removing  the west side of Fawn. They may also get a few of the patches down on the south part of Caribou. The concrete crew should be finishing up on Deer Trail, and heading around on Buckskin up to Stag and down Stag. Also filling in the patches on Reindeer if they can get the water pumped out and kept out. Hopefully the weather will be cooperating more with us, and things will move along.

May 8, 2019 Garcia will be continuing to pour concrete on the south/west side of Reindeer probably until early next week. Then the concrete crew should be moving over to what has been stoned on Deer Trail and Buckskin to start forming that and prepping it for concrete. Concrete removal shall be continuing on Buckskin up to Stag Dr and then head part way down Stag on the east side. For the residents on Deer Trail and Stag, I know parking is at a premium as Garcia gets into these areas, so please help out your neighbors if you can, by letting them utilize any driveway space that you can.
May 2, 2019 Friday 5/3/19, during the Garage Sale, crews will be pouring the section of street on Buckskin from Yearling to Reindeer. They should be starting early and finishing by noonish. There will be congestion in that area during the actual pouring because of the trucks blocking the lanes. After that is complete, the road shall be passable but maybe with slight delays for the workers to finish the concrete. Nothing else will be removed until Monday.
April 30, 2019 Crews have removed the south/west lane of Reindeer and are going to remove the north side of Deer Tr. As they turn out of Deer Tr. they will head north to Stag while removing the opposite side of Buckskin and the east side of Stage to SR 14. We realize it can be frustrating to wait on the concrete to go through its 7 day cure time, and everyone wants to get into their driveways as soon as possible but it's important to allow the concrete to cure. We are aware of residents that have been crossing across the barricaded pavement before it has been officially opened; please be aware that removing barricades and tape can be punishable by fines and penalties.
April 16, 2019 Crews have removed the south/west side of Buckskin. While they are waiting to get this formed and poured, removal will begin on the north side of Yearling starting 4/17/19.
April 12, 2019

Important Update from the Project Manager:

Crews are removing and pouring on Buckskin from Reindeer to the North on the west side until they reach Caribou.

There will be a section that will be poured Monday morning (4/15/19). Please keep in mind that the lanes will be blocked for periods of time. 

The crews will be aware you are there, but it may not be possible for them to move until they are at a good stopping point. When pouring concrete this is especially important. They only have so much time to get the concrete out of the truck, and it is easier to pour out each truck in one passing.

Please familiarize yourself with the alternate routes available in your addition, and utilitze those if at all possible.

Also, there have been concerns that some of the crew members are being impolite by not speaking to the residents. Please be assured that this is not because they are ill-mannered. The project representatives want to ensure that the residents receive the most up to date and accurate information possible. To avoid any unintentional miscommunication, the crews have been instructed to refer any inquiries to the project foreman on location or to the project manager.

If you have a question, please talk to a foreman out on the job, or call the project manager. We will assist where we can and appreciate those that have let us know of issues. We understand this is a hassle for everyone and we want to get out of your way as soon as we can.

April 5, 2019

Crews are getting the open areas on Yearling's south side and around the corner on the west side of Buckskin prepped for concrete on Monday.

Working on a section on the west side of Buckskin from Reindeer to the north. Work should continue on this section as the weather cooperates.

Putting underdrain in the section and will be getting that prepped for concrete

ALSO:
If anyone has issues getting to their house, mail, any concerns at all, please feel free to call the Project Manager to make her aware of these issues.

We will do what we can to accommodate the residents, but we cannot, if we are not aware. We are asking that all traffic on Buckskin be local traffic only and residents.

Please be patient while we are on this long, busy stretch, and possibly plan on taking another route if possible.

 

March 18 - 22, 2019  Structure and pipe work continuing on Yearling. Weather permitting, removal of concrete street and pouring of concrete on Yearling in a couple weeks
March 11 - 15, 2019 Contractor was able to continue work until PM rain on Wednesday and Thursday brought construction to a temporary halt
March 7, 2019 Work continues at SW corner of Yearling and Buckskin Intersection.
March 6, 2019 Garcia placed temporary backfill at NW corner of Yearling/Buckskin intersection and began work at SW corner of Yearling/Buckskin intersection
March 1, 2019 Garcia continued work at NW corner of Yearling/Buckskin Intersection and poured concrete collars around pipe  
February 28, 2019 Work continues at the NW Corner of Yearling and Buckskin.
February 27, 2019 Garcia removed barricades and cleaned reindeer of debris and began work at NW corner of Yearling and Buckskin
February 26, 2019 Reindeer Drive closed for concrete removal .
February 25, 2019 Garcia closed down Reindeer Road for pipe & inlet installation
February 21, 2019 Curb and gutter work on Buckskin Drive
February 19, 2019 Garcia cleaning up intersection at Stag and Buckskin.
February 18, 2019 Garcia closed down Stag/Buckskin to allow for intersection work across Buckskin. 
February 11-15, 2019  Work resumed with placement of pvc pipe
January 2019 Garcia Concrete completed work until after the holidays on 12/20/2018, the crews will return to begin installation of underground pipe and structures on Yearling.
December  2018 Along with continued work on the installation of underground structures, the contractor took advantage of the warmer days, completing the pouring of concrete streets in the west half of the project:  Roe, Buck Ct, Caribou from Buck Ct south and Yearling from Caribou to the cul de sac.
November 19-21, 2018 Crews removed concrete on Yearling and poured new surface on Roe, they will continue with concrete work as temperatures allow.  Garcia will focus on installing underground pipes and structures through the winter months when it becomes too cold to pour concrete
November 12-16, 2018 Garcia poured new concrete on Buck Ct., Caribou Dr. and Roe

 

November 5-9, 2018 - Crews began concrete removal on Roe before snow arrived at the end of the week

October 29 - November 2, 2018 - Crews removed concrete and installed underdrain on Buck Ct. 

October 22-26, 2018 - Pouring of concrete continued on Buck Ct.

October 15-19, 2018 - Garcia Concrete poured concrete on Caribou Dr. and Buck Ct.

October 8-12, 2018 - Contractor excavated and placed underdrain on Buck Ct. and poured concrete on Yearling and Caribou.

October 5, 2018 - Construction began on 9/28/18 with crews removing old concrete on Yearling, Caribou and Buck as well as prepping for the underdrain that was placed on Yearling. Pouring of new concrete began on Yearling.  The contractor plans to continue excavating on Buck.

September 17-21, 2018 - Pavement marked for contractor during the week so that crews may begin excavation work next week

September 6, 2018 - Weather permitting, Garcia Concrete hopes to begin construction the week of September 17th.

August 30, 2018:  - Garcia Concrete Construction will begin construction in mid-September.

You can meet the contractor and Public Works project representatives tonight! 

This project involves spot repair or reconstruction of concrete streets;
repair of deteriorated curbs, sidewalks and wing walks and installing ADA curb ramps. 
The majority of the construction will take place in public right-of-way.
We know street repair projects can be disruptive and inconvenient.
We want you to be well-informed about the project and to know who can answer your questions or resolve any construction issues. 
Please join us to meet project representatives from Public Works and Garcia Concrete.
Thursday, August 30th at 6:30 PM - Westview Alliance Church  - 9804 Illinois Road, Fort Wayne, IN  46804
 

PLEASE DO NOT MOVE BARRICADES

Newly poured concrete needs 7 days to cure. Do NOT move barricades and drive over concrete that is curing. It can damage the concrete, reduce the pavement’s life  -- causing it to crumble within months. Please be vigilant and stop people from moving barricades.

Parking: Residents may not have access to their driveway while work is being done on the section of their street. Please park away from construction and DO NOT block traffic lanes.

Trash & Recycling Collection: The night before collection day, residents should place their garbage and recycling containers near the curb, away from the barricades of construction zones for collection – which may be across the street or at the end of the cul-de-sac.

If garbage collection trucks are not able to get to your street, due to construction work, they will try to collect the next day, before construction begins in the morning. For more information, call 311.

Neighborhood Engagement: Public Works staff members have been meeting with neighborhood associations to give residents the opportunity to view work zones, meet the contractors and ask questions about work being done in their neighborhoods. For questions or concerns, you may reach the Division of Public Works by calling 311 or 427-8311.