INVESTING IN OUR NEIGHBORHOODS

 

The City will be investing in alley reconstruction throughout our neighborhoods.  This list will be updated with approximate start dates.

 

NEIGHBORHOOD - LOCATION

 

PROJECT STATUS

Bloomingdale Neighborhood 

North-south and east west alley
Bounded by:
Spring St., Fourth St.,  
Andrew St., Sherman Blvd. 

9/14/18 - Project has been awarded & contractor has met with the engineer.

9/26/18 - Construction began on 9/20/18 and is currently underway. Work is expected to be complete in early October, 2018.

10/12/18 - Construction complete

Creighton Home Neighborhood

"L" shaped alley
(east-west and short north-south)
Bounded by:
Home Ave., Beechwood Dr.,
South Wayne Ave., Fairfield Ave.

 9/26/18 - Project has been awarded. Contractor to meet with engineer for a final review of plans and to determine a start date for construction

12/7/18 - Contractor began alley removal mid-November and completed the substantial portion of concrete work at the end of November.

East Central Neighborhood

East-west alley bounded by:
Chute St. Ohio St.,
Hugh St., Eliza St.,
Francis St., Harmar St.,
Hugh St. Eliza St.

Construction completed June 2018

East Central Neighborhood

East-west alley bounded by:
Francis St., Chute St.,
E. Lewis St., Hugh St.

Construction completed August 2018

East Central Neighborhood

Alley bounded by:
E. Lewis St., Winter St.,
Hayden St., Lillie St

Construction completed late July 2018

East Central Neighborhood

North-south alley bounded by:
Lillie St., S. Anthony Blvd.,
Alliger St., Hayden St.

8/31/18 - Project is in final design phase

9/26/18 - Final plans complete, construction expected to begin in November, 2018

12/7/18 - Contractor began alley removal mid-November and started pouring the new surface on 12/4/18 

12/20/18 - Construction complete

Fairfield Neighborhood

East-west & north-south alley
bounded by:
Hoagland Ave., S. Harrison St.,
W. Leith St., Killea St.
(except the east 132.5 ft of the east-west alley)

Construction began 8/7/18 and is expected to be completed by mid-October

8/31/18 - Old surface has been excavated, prepping to pour new surface

9/3-9/7/18 - Workers began pouring new concrete

9/10-9/21/18 - Pouring of new concrete continues

9/24-9/28/18 - 95% of the concrete work is complete, backfilling and topsoil restoration begins

10/12/18 - Construction and restoration complete

Fairfield Neighborhood

North-south alley bounded by:
Fairfield Ave., Hoagland Ave.,
Kinnaird Ave. & Wildwood Ave.

Completed May 2018

Fairfield Neighborhood

North-south alley bounded by:
Webster St., S. Harrison St.,
E. Wildwood Ave., Killea St.

8/22/18 - Project begins excavation phase of construction

8/31/18 - Crews continue working on removal of concrete 

9/3-9/7/18 - Contractor prepping for new surface

9/10-9/14/18 - Pouring of new surface begins

9/17-9/21 - Pouring of new surface continues

9/24-9/28 - Alley remains closed to traffic to allow for the new surface to harden (cure)

10/2/18 - Construction and restoration completed

Hamilton Association

East-west alley bounded by:
W. Fourth St. / Schilling Ave.,
Third St. / Franklin Ave.

Completed June 2018

Hamilton Neighborhood 

Alley bounded by: 
Greenlawn Ave., Archer Ave., 
Oakland St., Sherman Blvd.

0243D

9/17/18 - Construction began in August with removal of old concrete.  Contractor poured new conrete today and it will need 7-14 days to cure (harden). 

9/24-9/28/18 - Alley remains closed to allow new concrete to continue to cure.

Restoration with seeding and mulching expected to begin around the first week of October

10/12/18 - Construction and restoration complete

Hamilton Neighborhood

Spring St., Fourth St.,
Oakland St., Sherman Blvd.
(north-south)

9/14/18 - Project has been awarded & contractor has met with the engineer. 

9/26/18 - Construction began on 9/20/18 and is currently underway. Work is expected to be complete in early October, 2018.

10/12/18 - Project complete

Historic South Wayne
Neighborhood:

East-west alley bounded by:
Kinnaird, W. Wildwood Ave.,
Indiana & South Wayne Ave.

9/26/18 - Project has been awarded & the contractor has met with the engineer for a final review of the plans.

Construction is expected to begin early October with a completion date of late October  

10/3/18 - Contractor began construction

Project completed 10/30/18

Northside Neighborhood

Alley bounded by:
Kentucky Ave., Crescent Ave., 
State Blvd., Nevada Ave.

8/31/18 - Project has been awarded and the excavation phase of construction is expected to begin within the week

9/4-9/7/18 - Contractor began removal of the old concrete

9/10-9/14/18 - Removal of old surface expected to continue into next week before prepping for pouring of new concrete

9/17-9/28/18 - Contractor continues excavation of old and pouring of new concrete along the length of the alley

10/12/18 - Contractor finished concrete work, beginning restoration.

10/30/18 - Project complete

Oakdale Neighborhood

North-south alley bounded by: 
Broadway, Beaver Ave., 
W. Oakdale Dr., Kinsmoor Ave.

 Completed - May 2018

Pettit-Rudisill
Neighborhood Association

North-south alley bounded by:
Weisser Park Ave., South Park Dr.,
E. Pettit Ave., and Congress Ave.

9/14/18 - The contractor has met with the project engineer and construction is expected to begin the first week of October. The scheduled completion date is 11/30/2018.

10/1/18 - Garcia Concrete will begin construction the second week of October

10/12/18 - Construction will begin 10/15/18.

Project completed 11/30/18

Pettit-Rudisill
Neighborhood Association

Alley bounded by:
E. Sherwood Terrace., E. Maple Grove Ave.,
Warsaw St., S. Monroe St.

Construction complete July 2018

Pettit-Rudisill
Neighborhood Association

North-south alley bounded by:
Gaywood Dr. on the east,
Spatz Ave. on the west,
E. Pettit Ave. on the south 
McKinnie Ave. on the north.

Construction completed July 2018

Pontiac Place Association

Alley bounded by:
Central Dr., Plaza Dr.,
E. Pontiac St., McKee St.

 9/4-9/7/18 - Contractor completed  removal of old surface

9/10-9/14/18 - Crews prepped for new surface and began pouring concrete

9/17-9/21/18 - Contractor continues pouring new surface 

10/12/18 - Concrete work complete, restoration underway

Project completed 10/30/18

South Wayne Neighborhood

East-west alley bounded by:
Beaver Ave., South Wayne Ave.,
W. Packard Ave., Kinnaird Ave.

9/14/18 - Project has been awarded.

Construction start date will be updated as soon as determined, with the expected completion date being mid-November 

10/1/18 - Contractor began removal of alley

10/11/18 - Finished removal, currently pouring new alley surface

Project completed November 2018