INVESTING IN OUR NEIGHBORHOODS

 

The City will be investing in alley reconstruction throughout our neighborhoods.  This list will be updated with approximate start dates.

 

NEIGHBORHOOD INTERSECTION/LOCATION STATUS
Bloomingdale Neighborhood  Alley Reconstruction: Spring St., Fourth St.,  Andrew St., Sherman Blvd. (n/s & e/w) 9/14/18 - Project has been awarded & contractor has met with the engineer. Construction start date will be updated as soon as available, with completion expected by October 2018
Creighton Home Neighborhood "L" shaped alley (east-west and short north-south), Home Ave., Beechwood Dr., South Wayne Ave., Fairfield Ave.  
East Central Neighborhood East-west alley bounded by Chute St. Ohio St., Hugh St., Eliza St., Francis St., Harmar St., Hugh St. Eliza St. Construction completed June 2018
East Central Neighborhood East-west alley bounded by Francis St., Chute St., E. Lewis St., Hugh St. Construction began in July is expected to be completed by 9/28/18.
East Central Neighborhood Alley bounded by E. Lewis St., Winter St., Hayden St., Lillie St. Construction completed late July 2018
East Central Neighborhood North-south alley bounded by: Lillie St., S. Anthony Blvd., Alliger St., Hayden St.  8/31/18 - Project is in final design phase
Fairfield Neighborhood East-west and north-south alley bounded by: Hoagland Ave., S. Harrison St., W. Leith St., Killea St. (except the east 132.5 feet of the east-west alley)

Construction began 8/7/18 and is expected to be completed by mid-October

8/31/18 - Old surface has been excavated, prepping to pour new surface

9/3-9/7/18 - Workers began pouring new concrete

9/10-9/14 - Pouring of new concrete continues

Fairfield Neighborhood North-south alley bounded by Fairfield Ave., Hoagland Ave., Kinnaird Ave. & Wildwood Ave. Completed May 2018
Fairfield Neighborhood north-south alley bounded by: Webster St., S. Harrison St., E. Wildwood Ave., Killea St.

8/22/18 - Project begins excavation phase of construction

8/31/18 - Crews continue working on removal of concrete 

9/3-9/7/18 - Contractor prepping for new surface

9/10-9/14/18 - Pouring of new surface begins

Hamilton Association East-West Alley bounded by: W. Fourth St. / Schilling Ave., Third St. / Franklin Ave. Completed June 2018
Hamilton Neighborhood 
0243D
Alley bounded by Greenlawn Ave., Archer Ave., Oakland St., Sherman Blvd.

9/17/18 - Construction began in August with removal of old concrete.  Contractor poured new conrete today and it will need 7-14 days to cure (harden). 

Restoration with seeding and mulching expected to begin around the first week of October

Hamilton Neighborhood Spring St., Fourth St., Oakland St., Sherman Blvd. (north-south)  9/14/18 - Project has been awarded & contractor has met with the engineer. Construction start date will be updated as soon as available, with completion expected by October 2018
Historic South Wayne Neighborhood: East-west alley bounded by Kinnaird, W. Wildwood Ave., Indiana & South Wayne Ave. Construction to begin late summer and is expected to be completed by the end of October
Northside Neighborhood Alley bounded by Kentucky Ave., Crescent Ave., State Blvd., Nevada Ave.

8/31/18 - Project has been awarded and the excavation phase of construction is expected to begin within the week

9/4-9/7/18 - Contractor began removal of the old concrete

9/10-9/14/18 - Removal of old surface expected to continue into next week before prepping for pouring of new concrete

Oakdale Neighborhood North-south alley bounded by: Broadway, Beaver Ave., W. Oakdale Dr., Kinsmoor Ave.  Completed - May 2018
Pettit-Rudisill Neighborhood Association north-south alley bounded by Weisser Park Ave., South Park Dr., E. Pettit Ave., and Congress Ave. 9/14/18 - The contractor has met with the project engineer and construction is expected to begin the first week of October. The scheduled completion date is 11/30/2018.
Pettit-Rudisill Neighborhood Association Alley bounded by E. Sherwood Terrace., E. Maple Grove Ave., Warsaw St., S. Monroe St. Construction completed July 2018, contractor completing restoration as of August 2018
Pettit-Rudisill Neighborhood Association North-South Alley bounded by Gaywood Dr. on the east, Spatz Ave. on the west, E. Pettit Ave. on the south &  McKinnie Ave. on the north. Construction completed July 2018
Pontiac Place Assn. Alley bounded by Central Dr., Plaza Dr., E. Pontiac St., McKee St.

 9/4-9/7/18 - Contractor completed  removal of old surface

9/10-9/14/18 - Crews prepped for new surface and began pouring concrete

South Wayne Neighborhood East-west alley bounded by: Beaver Ave., South Wayne Ave., W. Packard Ave., Kinnaird Ave. 9/14/18 - Project has been awarded. Construction start date will be updated as soon as determined, with the expected completion date being mid-November