Investing In Our Neighborhoods

 2019 Alley Resurfacing Projects

The City will be investing in alley reconstruction throughout our neighborhoods. This list will be updated with further project and construction schedules as established
Boerger’s Addition
North/south alleys (2) Between W. Foster Pkwy., Lexington, Buell and Hoagland
July 2019 Site survey underway, design phase will begin once survey complete
May-19 Engineers working on location survey
Apr-19 Engineering Phase
Mar-19 Engineering Phase – construction expected to begin late Fall 2019
Bloomingdale Neighborhood
North/south alley Between Wells, Cass, W. Fourth and Third
July 2, 2019 Malott Contracting began construction 7/1/2019 
June 4, 2019 Project has been awarded to Malott Contracting, construction start date will be provided once determined
May-19 Project is scheduled to be bid and awarded early June. Construction should begin mid-late June depending on contractor schedule.
Apr-19 Final Design Phase - completed
Mar-19 Engineering Phase – construction expected to begin Summer 2019
Francis Slocum Neighborhood:
East/west alley Between Carew, Rolston, E. State Blvd. and Lynn
July-19 Project awarded to Key Concrete, construction is expected to begin early August
May-19 Project is scheduled to go out to bid in early June, construction should begin mid to late June with an estimated completion of 8/30/19
Apr-19 Phase – Final Design
Mar-19 Phase – Engineering – Construction expected to begin Summer 2019
East/west alley Between Lynn Ave, Dodge, Rolston and Beacon
June-19 Construction completed
May-19 Construction begins 5/17/19
Apr-19 Phase – Final Design
Mar-19 Phase – Engineering – Construction expected to begin Summer 2019
Hoagland Masterson Neighborhood
North/south alley Between W. Wallace, W. Masterson, S. Harrison and S. Calhoun
North/south alley Between W. Wallace, W. Masterson, Webster and Harrison
June 11, 2019 Construction completed
Mar-19 Construction began 3/18/19 with an expected completion date of June 2019
Mount Vernon Park
East/west alley Between McKinnie Ave., Senate, Smith and Bowser
May-19 Construction expected to begin early fall
Apr-19 Engineers working on location survey
Mar-19 Engineering Phase
Northside Neighborhood
North/south alleys (2) Between E. State Blvd., Forest, California and Florida
July 16, 2019 Drafting and engineering phase complete - project entering bidding phase
May-19 Survey complete, drafting begins
Apr-19 Engineers are working on location survey
Mar-19 Engineering Phase – construction expected to begin Summer 2019

Oakdale Community 

(the following 3 alleys are combined into one project)

North/south alley between W. Rudisill, W. Oakdale, South Wayne and Arlington
North/south alley between W. Rudisill, W. Foster Pkwy., South Wayne and Arlington
East/west alley between Arlington, South Wayne, W. Oakdale and W. Rudisill

Jul-19 Project in design phase 

Oxford Community 

(the following 3 alleys are combined into one project)

East/west alley between Reed St, Winter St, north/south alley and Winter
North/south alley between the east/west alley, Colerick St., Reed St. and Winter St
North/south alley between E. Pontiac, Colerick, Winter and Lillie St.

July-19 Project in bidding phase
May-19 Final Design Phase
Apr-19 Survey work completed
Mar-19 Engineering Phase – construction expected to begin late Summer 2019

Oxford Community 

North/south alley between Oxford, Grier, Oliver and Bowser
July-19 Construction completed
June 19, 2019 Contractor began construction on 6/12/19 with removal of pavement
May-19 Project awarded to contractor, Malott Contracting on 5/21/19, construction expected to begin early/mid-June
Apr-19 Engineering phase completed early April, project advertised for bid at end of month
Mar-19 Engineering Phase – construction expected to begin Summer 2019

Pettit Rudisill 

(the following two alley are combined into 1 project)

North/south alley between Rudisill Blvd., Baxter, Smith and Oliver
East/west alley between Smith, Oliver, Rudisill and Baxter

June 21, 2019 Weather permitting construction will begin week of June 24, 2019 (mid-week), work is expected to be completed August 2019
May-19 Project awarded to contractor, MS Concrete on 5/21/19, construction expected to begin early summer
Apr-19 Engineering Phase completed early April, project advertised for bid at the end of the month
Mar-19 Engineering Phase – engineers completing survey work

Pettit Rudisill 

North/south alley between McKinnie, Baxter, Avondale & Warsaw
July-19 Project has been awarded to  Malott Contracting 
May-19 Project to be bid early June
Apr-19 Survey work completed
Mar-19 Engineering Phase – construction expected to begin Summer 2019

Pettit Rudisill  

East/west alley Between Fox Ave, N/S alley, W. Creighton and W. Dewald St.
North/south alley Between E/W alley, W. Dewald, Fox Ave. and Fairfield Ave.
May-19 Engineers working on location survey
Apr-19 Engineering Phase
Mar-19 Engineering Phase – construction expected to begin late Summer 2019

Pettit Rudisill 

North/south alley Between Killea, W. Wildwood, Shawnee and Webster 
May-19 Engineers working on location survey
Apr-19 Engineering Phase
Mar-19 Engineering Phase – construction expected to begin late Summer 2019

South Wayne Neighborhood

East/west brick alley Between Beaver, Indiana, W. Wildwood and Kinnaird
May-19 5-18-19 – Construction complete, contractor completing final restoration
5-8-19 – Contractor begins brick installation
Apr-19 4-22-19 – Construction began with excavation of old brick and installation of sub-base
Mar-19 Project out for bid and awarded to contractor

Tyler's Addition 

(the following 2 alleys are combined into one project)
North/south alley Between: W. Dewald to intersection of east/west alley
East/west alley Between: Fairfield, Hoagland, W. Dewald and W. Creighton
July-19 Construction beginning 7/15/19 & is expected to be completed by the end of August
June-19 Project has been awarded to Key concrete
May-19 Engineers working on location survey
Apr-19 Engineering Phase
Mar-19 Engineering Phase – construction expected to begin late Summer 2019

Williams Woodland Park

East/west alley Between: S. Clinton, Lafayette, Dalman Ave & E. Wildwood
July 16, 2019 Project is in bidding phase, construction expected to begin late summer and be completed late fall

Williams Woodland Park 

North/south alley Between: W. Suttenfield, W. Taber St., Webster & Harrison
July-19 Construction expected to begin late July / early August
June 19, 2019 Project has been awarded to contractor Mallott Contracting
May-19 Project to be advertised for bid at the end of the month, with expected bid and award early June
Apr-19 Engineering Phase completed
Mar-19 Engineering Phase – construction expected to begin mid-summer 2019 and completed by September 2019