PWlogoweb

Investing in our Neighborhoods

Harris Road Widening

Start Date

July 16, 2019

Estimated Completion
Date

Fall 2019 Actual Completion
Date
August 2, 2019

Contractor

Brooks Construction Investment $94,376

Project Information
and Updates

Road widening from W. Coliseum Blvd. to 390 ft. south, to accommodate a dedicated left turn lane and 2 through lanes, concrete curb construction, pavement markings and an asphalt overlay

August 2, 2019

Project complete

July 30, 2019

Crews completed pavement markings, road now open.  Topsoil and seed placed for restoration

July 23, 2019

Excavation completed, Brooks construction starting to pave surface

July 16, 2019

Harris Road closure is now in effect, crews have begun construction with removal of concrete headwall

June 28, 2019

Construction is tenatively set to begin the week of July 15, 2019

May 2019

Project has been awarded to contractor, Brooks Construction. 
Will update construction start date after the engineer and contractor meet to review the plans and schedule

April 2019

The project is being advertised for bid on April 5th and April 12th, 2019, it is expected to be bid out and awarded within the next month

March 2019

The design phase is completed and engineer is preparing the project to be bid

 

PLEASE DO NOT MOVE BARRICADES

Newly poured concrete needs 7 days to cure. Do NOT move barricades and drive over concrete that is curing. It can damage the concrete, reduce the pavement’s life  -- causing it to crumble within months. Please be vigilant and stop people from moving barricades.

Parking: Residents may not have access to their driveway while work is being done on the section of their street. Please park away from construction and DO NOT block traffic lanes.

Trash & Recycling Collection: The night before collection day, residents should place their garbage and recycling containers near the curb, away from the barricades of construction zones for collection – which may be across the street or at the end of the cul-de-sac.

If garbage collection trucks are not able to get to your street, due to construction work, they will try to collect the next day, before construction begins in the morning. For more information, call 311.

Neighborhood Engagement: Public Works staff members have been meeting with neighborhood associations to give residents the opportunity to view work zones, meet the contractors and ask questions about work being done in their neighborhoods. For questions or concerns, you may reach the Division of Public Works by calling 311 or 427-8311.