PWlogoweb

Investing in our Neighborhoods

Decatur Road Sidewalk Connection, Ph 2

Start Date August 1, 2019
Approx. Completion  Late September 2019  Acutal Completion August 28, 2019
Contractor Brooks Construction  Investment $106,512.00
Project Description Construct concrete sidewalk, ADA curb ramps and install underground culvert pipe from Gable Road to 600' north of Gable Road

 

September 3, 2019 Construction complete
August 1, 2019 Brooks Construction began construction today - crews began removal of drainage pipe, vegetation and began grading the ditch line and sidewalk. They also stoned the first 100' of sidewalk from the south heading north. 
July 25, 2019 Contractor plans to begin construction on 7/29/19
June 21, 2019 Project was awarded to Brooks Construction on 6/18/19, construction start date will be provided after the pre-construction meeting is held (July 2, 2019) and schedule is determined
June 2019 Project information will be updated once bid and awarded later this month
May 2019

Final design phase completed, project advertised for bid

 

 

PLEASE DO NOT MOVE BARRICADES

Newly poured concrete needs 7 days to cure. Do NOT move barricades and drive over concrete that is curing. It can damage the concrete, reduce the pavement’s life  -- causing it to crumble within months. Please be vigilant and stop people from moving barricades.

Parking: Residents may not have access to their driveway while work is being done on the section of their street. Please park away from construction and DO NOT block traffic lanes.

Trash & Recycling Collection: The night before collection day, residents should place their garbage and recycling containers near the curb, away from the barricades of construction zones for collection – which may be across the street or at the end of the cul-de-sac.

If garbage collection trucks are not able to get to your street, due to construction work, they will try to collect the next day, before construction begins in the morning. For more information, call 311.

Neighborhood Engagement: Public Works staff members have been meeting with neighborhood associations to give residents the opportunity to view work zones, meet the contractors and ask questions about work being done in their neighborhoods. For questions or concerns, you may reach the Division of Public Works by calling 311 or 427-8311.