Investing in our Neighborhoods


2020 Major Street Improvement Projects 

Project List - Click on the project for additional details 
Ardmore Avenue Improvements 
(Airport Expressway to Second Street)

Start Date:  March  2019
Est.Completion Date: Spring 2020

Contractor: E&B Paving
Investment: $3.6 Million

Hobson Road Street Improvements

Start Date: July, 2020
Est. Completion Date: November, 2020

Contractor: Brooks Construction
Investment: $2,525,396.00

Maplecrest Road Widening - Phase 1

Start Date: October 14, 2019 
Estimated Completion: November 2020 

Contractor E & B Paving
Investment: $6,702,333

Maplecrest Road Widening - Phase 2 (Coming Soon)  
Goshen Road Reconstruction

Start Date: July, 2019
Est. Completion Date: October, 2020

Contractor: Primco, Inc
Investment: $5.2 Million

   
State Boulevard

Start Date: Spring 2019
Est. Completion: Spring 2021

Contractor: Primco, Inc
Investment: $8.2M
(80% Federal Funds, 20% Locally Funded)

St. Joe Center Road (Clinton to Campus Court) Start Date: April 15, 2019
Est. Completion Date: June 2020

Contractor: E&B Paving
Investment: $2.8 Million