Investing in our Neighborhoods


Concrete Street Repairs  

Project Locations
Aboite Meadows Concrete Street Repairs 05/01/20 - Construction complete
Aspen Village Concrete Street Repairs
  • Est Start Date: September 2020
    Est End Date: Summer 2021
  • Contractor: Malott Contracting
    Investment: $1,644,456.00
  • Project Status:
    12/18/20 - Construction (12%)
Challenger Parkway Street Repairs 
  • Start Date: September 30, 2020
    Est End Date: Spring 2021
  • Contractor: Key Concrete
    Investment: $1,644,456.00
  • Project Status:
    11/12/20 - Construction complete
Fallen Timbers - Blue Jacket Run
  • Start Date: August 13, 2020
    Est End Date: September 2020
  • Contractor: Key Concrete
    Investment: $549,892.00
  • Project Status:
    09/23/20 - Construction Complete
Glenwood Park Concrete Street Repairs 
  • Est Start Date: October 19, 2020
    Est End Date: May 2021
  • Contractor: Primco, Inc
    Investment: $923,020.89
  • Project Status:
    12/09/20 - Construction (30%)
Greater McMillen Park Concrete Street Repairs, Ph 3
  • Start Date: August 13, 2020
    Est End Date: September 2020
  • Contractor: Key Concrete
    Investment: $454,368.00
  • Project Status:
    09/23/20 - Construction Complete
Miscellaneous Right Of Way Concrete Repair Project 
  • Project includes replacement of various streets, curbs, sidewalks, ramps, medians, curb islands, or other areas in need of grading for drainage.
Pine Valley Phase III - Trader's Pointe 08/25/20 - Construction Complete
Springwood-Orchard Woods Concrete Street Repairs, Ph.1
  • Start Date: August 12, 2020
    Est End Date: Early summer 2021
  • Contractor: Hipskind Concrete
    Investment: $2,057,778.00
  • Project Status:
    12/09/20 - Construction (70%)
    ***Contractor will be placing soil for restoration this week and then suspending all work until March of 2021. The contractor will be removing all barricades by December 11th. There will be no traffic or pedestrian closures/restrictions until March of 2021 (weather permitting)
Tanbark Community Concrete Street Repairs
  • Start Date: July 07, 2020
    End Date: October 22, 2020
  • Contractor: Hipskind Concrete
    Investment: $1,477,778.00
  • Project Status:
    10/22/20 - Construction Complete
Woodhurst Addition Concrete Street Repairs
  • Start Date: September 2019
    End Date: July 24, 2020
  • Contractor: Hipskind Concrete
    • Project Status:
      074/24/20 - Construction Complete

  

Concrete Street Repairs

Current and Upcoming Projects

Aspen Village Concrete Street Repairs

  • Est Start Date: September 2020
    Est End Date: Summer 2021
  • Contractor: Malott Contracting
    Investment: $1,644,456.00
  • Project Status:
    12/18/20 - Construction (12%)

Aspen Village Concrete Street Repairs

  • Est Start Date: September 2020
    Est End Date: Summer 2021
  • Contractor: Malott Contracting
    Investment: $1,644,456.00
  • Project Status:
    12/18/20 - Construction (12%)