Hoagland Masterson Nbhd - (east/west brick alley)
- W. Dewald St to W. Creighton
Webster St to Hoagland Ave
|
- Start Date: 10/14/2020
Est End: Fall 2020
- Contractor: Garcia Concrete
Investment: $145,278.50
- Project Status:
12/02/20 - Construction complete
|
Hoagland Masterson Nbhd - (east/west brick alley)
- W. Dewald St to W. Creighton
S. Harrison St to Webster St
|
- Start Date: October 1, 2020
Est End: Late Fall 2020
- Contractor: Key Concrete
Investment: $85,370.00
- Project Status:
11/04/20 – Construction complete
|
West Central - (east/west brick alley)
- Van Buren to Jackson
Wayne St to Washington Blvd
|
- Est Start: August 2020
Est End: Fall 2020
- Contractor: Key Concrete Inc.
Investment: $123,340.00
- Project Status:
08/26/20 - Construction Complete
|
West Central - (east/west brick alley)
- Wayne St to Washington Blvd
Union St to Rockhill
|
- Est Start: August 2020
Est End: Fall 2020
- Contractor: Key Concrete
Investment: $128,110.00
- Project Status:
08/26/20 - Construction Complete
|