Investing in our Neighborhoods


Bridge Improvement Projects 

Project Locations
Bluffton Road Bridge 

Project consists of a bridge superstructure replacement. This is a federally funded project. 
  • Est. Start Date: 2024
    Est. Completion Date: 2025
Goeglein Road Bridge 

Project consists of a bridge superstructure replacement. This is a federally funded project
  • Est. Start Date: 2025
    Est. Completion Date: 2026
State Blvd Bridge at Bullerman Drain

Replacement of bridge located along East State Blvd between Bellshire & Maysville,

including retaining walls and sidewalk 
  • Start Date: June  2020
    Est End: Late October, 2020
  • Contractor: Primco, Inc.
    Investment: $1,531,412.46
  • Project Status: 
    December 2020 - Construction substantially complete - beginning restoration work

US 27 (Northbound Spy Run) Bridge over St. Mary's River

Project consists of a bridge superstructure replacement and beautification project.

This is a joint project between INDOT and the City. It is an INDOT lead project. 

pdfClick to view concept plans 

  • Est. Start Date: 2022
    Est. Completion Date: 2024
Van Buren Street Bridge

Project consists of a bridge superstructure replacement. Project is planned to open bids in October.
  • Est. Start Date: Winter 2020
    Est. Completion Date: Spring 2022
  • Contractor: Primco, Inc.
    Investment: TBA
  • Project Status: 
    December 2020 - Project has been awarded to Primco, Inc. and pre-construction meeting was held