Project Locations |
Bluffton Road Bridge
Project consists of a bridge superstructure replacement. This is a federally funded project. |
- Est. Start Date: 2024
Est. Completion Date: 2025
|
Goeglein Road Bridge
Project consists of a bridge superstructure replacement. This is a federally funded project |
- Est. Start Date: 2025
Est. Completion Date: 2026
|
State Blvd Bridge at Bullerman Drain
Replacement of bridge located along East State Blvd between Bellshire & Maysville, including retaining walls and sidewalk |
- Start Date: June 2020
Est End: Late October, 2020
- Contractor: Primco, Inc.
Investment: $1,531,412.46
- Project Status:
December 2020 - Construction substantially complete - beginning restoration work
|
US 27 (Northbound Spy Run) Bridge over St. Mary's River
Project consists of a bridge superstructure replacement and beautification project. This is a joint project between INDOT and the City. It is an INDOT lead project.
Click to view concept plans
|
- Est. Start Date: 2022
Est. Completion Date: 2024
|
Van Buren Street Bridge
Project consists of a bridge superstructure replacement. Project is planned to open bids in October. |
- Est. Start Date: Winter 2020
Est. Completion Date: Spring 2022
- Contractor: Primco, Inc.
Investment: TBA
- Project Status:
December 2020 - Project has been awarded to Primco, Inc. and pre-construction meeting was held
|