Investing in our Neighborhoods


2021 Alley Reconstruction Projects

Project Locations

Fairmont Nbhd

North/South Alley - Between W Foster Parkway, W Branning Ave, S Wayne Ave & Arlington Ave. 

Project Status: : 3/15/21 - Completing the bidding phase

Est Start: : April 2021 
Est End: July 2021

Contractor: TBD
Investment: TBD

Illsley Place - 

East/West alley between Broadway, Beaver Ave,W. Oakdale Dr, Illsley Drive

Project Status:  3/15/21 - Final design

Est Start: April 2021 
Est End: July 2021

Contractor: TBD
Investment: TBD

Oxford Community Assoc -

North/South alley between E Pontiac, Colerick, Lillie St & S Anthony Blvd

Project Status:  3/15/21 -Engineering work beginning

Est Start: Summer 2021
Est End: Late Summer 2021

Contractor: TBD
Investment: TBD

Renaissance Pointe Nbhd - 

North/South alley(s) between: Milan St., E. Pontiac St., S Anthony Blvd & Lillie St and
Lahmeyer St, E Pontiac, Winter & Lillie St

Project Status:  3/15/21 - Engineering phase (95% complete)

Est Start: Fall 2021
Est End: Fall 2021

Contractor: TBD
Investment: TBD

South Calhoun - 

North/South & East/West, T-shaped alley between S. Calhoun, Clinton St, Lexington Ct & McKinnie

Project Status:  3/15/21 - Final design

Est Start: Late Spring 2021
Est End: Fall 2021

Contractor: TBD
Investment: TBD