City Utilities has hired a contractor to replace a deteriorating water main on Doan Drive between South Calhoun Street and Noll Avenue.  The existing cast iron water main has outlived its useful life.  It will be replaced with approximately 400 linear feet of plastic water main that has an expected future life of 75 to 100 years. The  installation will be done using horizontal directional drilling. 

Construction Project Manager
Justin Eakright
260-427-2644
This email address is being protected from spambots. You need JavaScript enabled to view it.
 
 

City Utilities is designing a project that will improve drainage by installing new storm sewers, replacing portions of the existing stormwater management infrastructure and regrading areas so that more stormwater runoff will be directed into the storm sewer system.

Design Manager
Landon Geiger
260-427-8586
This email address is being protected from spambots. You need JavaScript enabled to view it.
 

pdfProject Fact Sheet

pdfProject Area Map

 

Beginning in August 2018, Lawnscape Site Development, Inc., working for City Utilities, will install new storm sewer pipe and inlets on a  portion of Karen Avenue west of Reed Road and behind homes on Kingsley Drive south of Vance Avenue. 

Construction Manager - Nick Rupley
260-427-5576

This email address is being protected from spambots. You need JavaScript enabled to view it.

pdfMeet the Contractor Meeting invitation - July 23, 2018 

pdfProject Fact Sheet

pdfProject Area Map

City Utilities is designing a project to stop erosion and stabalize the banks of the ditch south of St. Croix Drive in the Sanibel Acres addition.  The work will stabalize approximately 300 linear feet of ditchbank between Hobson Road and Cherrystone Court.

Design Manager
Michael Saadeh
260-427-5118
This email address is being protected from spambots. You need JavaScript enabled to view it.
 

pdfProject Fact Sheet

pdfProject Area Map

City Utilities is working to design a two-phased project that will improve drainage and reduce street flooding along Hessen Cassel Road from Oxford Street south to the City limits.

Phase 2 Design Update Meeting - November 26, 2018

pdfDesign update meeting invitation - English

pdfDesign update meeting invitation - Spanish

pdfDesign update meeting invitation - Burmese

Phase 1 of the project will extend from Oxford Street to Stardale Drive.

pdfPhase 1 Design Meetings Invitation - June 7 & 11, 2018

Phase 2 of the project will extend from Stardale Drive to Brentley Drive

pdfPhase 2 Design Meetings Invitation -- June 18 & 21, 2018

pdfProject Fact Sheet

pdfProject Area Map

Page 1 of 2