City Utilities is committed to updating and improving its sewer system to meet federal mandates and protect river water quality by significantly reducing the number of combined sewer overflow events (CSOs). Sewer system improvement plans are described in several documents that have been prepared by City Utilities and reviewed and approved by the US Environmental Protection Agency.

The Combined Sewer Overflow Long Term Control Plan (LTCP) includes general descriptions of projects the City Utilities will construct to reduce the amount of combined sewage being discharged to the St. Joseph, St. Marys and Maumee Rivers during rain fall and snow melt.

The Capacity Management, Operations and Maintenance (CMOM) program is an outline of how City Utilities will maintain and operate the sanitary sewer systems.

The LTCP and the CMOM have been incorporated into a Consent Decree - a legally binding document entered into by the City Utilities, the US EPA, the Indiana Department of Environmental Management and the US Department of Justice. The Consent Decree may be enforced by a federal judge and it contains provision for City Utilities to be fined and penalized for failure to carry out the LTCP and the CMOM. The Consent Decree also outlines steps City Utilities will take to eliminate sanitary sewer overflows.

 City Utilities also operates the combined sewer system according to a Combined Sewer System Operation Plan (CSSOP). This document was created to comply with the US EPA's Combined Sewer Overflow Control Policy and specified many of the activities City Utilities undertakes to operate the combined sewer system.