Main and Berry streets at their respective intersections with Ewing Street are scheduled to reopen Wednesday, July 6, 2011, as the Ewing Street Storm Sewer Project enters its final phase. Ewing north of Berry will be open to vehicle and pedestrian traffic at that time.

Ewing between Berry and Wayne streets is scheduled to remain closed through July 30. The detour route for northbound Ewing Street traffic will continue to be Wayne Street to Harrison Street to Superior Street.

The contractor, Crosby Excavating Inc., will be responsible for placement and maintenance of all warning signs and barricades.

For further information or for problems that may develop contact the Traffic Engineering Department at 427-1172.