Investing in our Neighborhoods


Major Street Improvement Projects

Project List (Click on the project for additional details)
Ardmore Avenue Improvements 
(Airport Expressway to Second Street)
  • Start Date:  March  2019
    Est.Completion Date: September 2020
  • Contractor: E&B Paving
    Investment: $3.6 Million
  • Project Status -
    • September 23, 2020: Construction is substantially complete

Hobson Road Street Improvements

Project includes pavement reconstruction on Hobson Road as well as conversion from 4 lanes to 3 lane. This will allow for the installation of new sidewalks on both sides of the road, providing increased safety and accessibility for pedestrian traffic.

  • Start Date: July, 2020
    Est. Completion Date: November, 2020
  • Contractor: Brooks Construction
    Investment: $2,525,396.00
  • Project Status -
    • December 23, 2020: Construction (60%)
      Construction is on hold for the winter season and is planned to resume (weather permitting) March of '21. There may be intermittent minor restrictions as crews work on traffic signalization upgrades during this timeframe. 
Leesburg Road Extension Project
  • Est. Start Date: July, 2023
    Est. Completion Date: Spring 2025
  • Project Status -
    • December 2020: Survey work has been started
Ludwig Road Relocation Project
  • Est. Start Date: Late 2022
    Est. Completion Date: Spring 2024
  • Project Status -
    • December 2020:  Design work and utility coordination underway
Maplecrest Road Widening - Phase 1
  • Start Date: October 14, 2019 
    Estimated Completion: November 2020 
  • Contractor E & B Paving
    Investment: $6,702,333
  • Project Status -
    • 12/03/2020 - Construction complete

Maplecrest Road Widening - Phase II 

The last phase of the Maplecrest Road project includes road widening to 4 lanes with a center turn lane, sidewalk, trail, lighting, landscaping and signal improvements. The project will provid better mobility for drivers, bikers and walkers with access to schools and commercial facilities.

  • Est. Start Date: October or November 2020
    Est. Completion Date: Fall 2021
  • Contractor: Phend & Brown
    Investment: $4,693,400 total of which 80% federally funded.
  • Project Status -
    • December 2020 - Construction (1%).  Work is on hold for winter, no further lane restrictions will occur until the weather allows in the spring
Goshen Road Reconstruction
  • Start Date: July, 2019
    Est. Completion Date: October, 2020
  • Contractor: Primco, Inc
    Investment: $5.2 Million
  • Project Status - 
    • October 2020 - Construction Complete

State Boulevard Realignment 

This multi-phase project includes the comprehensive improvement, realignment and reconstruction of State Boulevard from Spy Run Avenue to Cass Street. The project is designed to reduce traffic congestion, improve traffic flow, improve sight distance and geometrics, improve bicycle and pedestrian facilities, alleviate roadway flooding and improve corridor connectivity along State Boulevard.

  • Start Date: Spring 2019
    Est. Completion: Spring 2021
  • Contractor: Primco, Inc
    Investment: $8.2M - (80% Federal Funds, 20% Locally Funded)
  • Project Status - 
    • October 30, 2020: Construction completed, tree planting work remains

St. Joe Center Road (Clinton to Campus Court)

 

  • Start Date: April 15, 2019
    Est. Completion Date: Summer 2021
  • Contractor: E&B Paving
    Investment: $5,353,110.00
  • Project Status - 
    • December 2020:  Construction (50%)
      ***Frontier Communications utility relocations are almost complete.  Construction planned to resume in the spring.